Solar project BHCT G14, Pueblo County

Solar project BHCT G14, Pueblo County is a 120 MW solar request withdrawn in the West interconnection queue, in Pueblo County, Colorado, connecting to Black Hills Colorado Electric.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2014 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
BHCT G14
Grid region
West (non-ISO utilities)
Utility / transmission owner
Black Hills Colorado Electric
Connection point (POI)
Reader-Pueblo Airport 115 kV
Location
Pueblo County, Colorado
Technology
Solar: 120 MW
Total requested
120 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
19 September 2014
Proposed online date
December 2016

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Pueblo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem