Requests shown3320 MW
Active in queue1,929 MW13 requests
Agreement signed339 MW4 requests
Withdrawn327,189 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-TC-2021-06, Logan County
Onshore wind
200 MWOperating Logan, COWest Mar 20212021
Solar project GI-TC-2021-07, Delta County
Solar
80.0 MWOperating Delta, COWest Mar 20212024
Solar project GI-TC-2021-04, Las Animas County
Solar
40.0 MWOperating Las Animas, COWest Mar 20212024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)