United States โ€บ Grid โ€บ Interconnection queues โ€บ California

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in California (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown481189.0 GW
Active in queue56.5 GW118 requests
Agreement signed0.0 MW0 requests
Withdrawn481189.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

481 requests ยท page 1 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Cuatro Vientos
Wind + storage
3,527 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Chokecherry and Sierra Madre Wind Energy Project
Onshore wind
3,290 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Ventura Wind
Onshore wind
2,482 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Monterey Wind
Onshore wind
2,462 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Oaks Wind
Onshore wind
2,460 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Charlie Wind
Onshore wind
2,460 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Boson
Solar + storage
2,347 MWWithdrawn / abandoned Kern, CACAISO Apr 2023target 2028
Ethan Creek
Onshore wind
1,870 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Gema Hybrid
Solar + storage
1,547 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Two Bunch Palms
Battery storage
1,518 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Southern Sierra PSP
Other
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Helms PSP Uprate
Battery storage
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Hydro project Q499, Riverside County
Hydro
1,300 MWWithdrawn / abandoned Riverside, CAWest Mar 2023target 2027
White Hills Solar Project
Solar + storage
1,278 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Borderline Solar
Solar + storage
1,268 MWWithdrawn / abandoned Inyo, CACAISO Apr 2023target 2028
Magic Valley Wind 1
Wind + storage
1,239 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Redwood Coast Offshore Wind 2
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Redwood Coast Offshore Wind 1
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Whispering Sands Solar
Solar + storage
1,202 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Herculean
Solar + storage
1,198 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Meson
Solar + storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
MidBishop Energy Storage
Battery storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Titan Power
Battery storage
1,160 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Nightcap
Gas
1,122 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2023target 2028
Elixir
Gas
1,101 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Hideout
Gas
1,101 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Taurus Wind
Wind + storage
1,088 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Blackbird
Solar + storage
1,057 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Egret
Solar + storage
1,057 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Heron
Solar + storage
1,056 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
FiveGB
Solar + storage
1,041 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Algodones Storage
Battery storage
1,039 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Harquahala Sunrise 3
Solar + storage
1,038 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Diablo Sands Energy Storage
Battery storage
1,036 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Rumorosa Wind
Onshore wind
1,029 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Skylar Verano Solar
Solar + storage
1,027 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Glyder
Solar + storage
1,026 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Frontera
Solar + storage
1,018 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Spotted Horse
Solar + storage
1,016 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Laramide Storage
Battery storage
1,000 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Greyhound Storage
Battery storage
1,000 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Ripple Solar
Solar + storage
946 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Nathan Creek
Onshore wind
935 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Jonathan Creek
Onshore wind
935 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Yuha Desert Battery Storage 2
Battery storage
900 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Wonder Solar
Solar + storage
892 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Cosmos
Battery storage
874 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Magic Valley Wind 2
Wind + storage
871 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Blue Star Energy Storage
Battery storage
829 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Brea Linda Energy Storage
Battery storage
829 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Page 1 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)