Solar + storage project Q2409, Navajo County Solar + storage |
2,626 MW | In study |
Navajo, AZ | West |
Feb 2024 | target 2028 |
Battery storage project Q2405, Maricopa County Battery storage |
1,020 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2033 |
Solar + storage project Q2417, Maricopa County Solar + storage |
843 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Solar + storage project Q2412, Navajo County Solar + storage |
822 MW | In study |
Navajo, AZ | West |
Feb 2024 | target 2028 |
Gas project 174, Pima County Gas |
800 MW | In study |
Pima, AZ | West |
Jun 2024 | target 2027 |
Solar + storage project Q2415, Maricopa County Solar + storage |
600 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Other project Q561, Maricopa County Other |
600 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2029 |
Solar + storage project Q2406, Maricopa County Solar + storage |
565 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2029 |
Other project 2024-G4, Mohave County Other |
550 MW | In study |
Mohave, AZ | West |
Apr 2024 | target 2027 |
Other project Q564, Maricopa County Other |
500 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Solar + storage project Q563, Pinal County Solar + storage |
500 MW | In study |
Pinal, AZ | West |
May 2024 | target 2028 |
Battery storage project 2024-MP2, Mohave County Battery storage |
500 MW | In study |
Mohave, AZ | West |
Jan 2024 | target 2028 |
Battery storage project 2024-MP1, Mohave County Battery storage |
500 MW | In study |
Mohave, AZ | West |
Jan 2024 | target 2028 |
Other project Q567, Maricopa County Other |
450 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Other project Q560, Maricopa County Other |
425 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Battery storage project Q2413, Pinal County Battery storage |
409 MW | In study |
Pinal, AZ | West |
Feb 2024 | target 2027 |
Gas project Q2403, Maricopa County Gas |
398 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Other project Q553, Navajo County Other |
340 MW | In study |
Navajo, AZ | West |
May 2024 | target 2028 |
Wind + storage project 2024-G7, Yavapai County Wind + storage |
313 MW | In study |
Yavapai, AZ | West |
Nov 2024 | target 2028 |
Onshore wind project 2024-G5, Mohave County Onshore wind |
300 MW | In study |
Mohave, AZ | West |
Aug 2024 | target 2029 |
Other project Q570, Yuma County Other |
300 MW | In study |
Yuma, AZ | West |
May 2024 | target 2028 |
Solar + storage project Q2402, Maricopa County Solar + storage |
300 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2027 |
Solar + storage project 2024-G3, Maricopa County Solar + storage |
260 MW | In study |
Maricopa, AZ | West |
Mar 2024 | target 2027 |
Other project Q558, Maricopa County Other |
250 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Solar + storage project Q569, Pinal County Solar + storage |
250 MW | In study |
Pinal, AZ | West |
May 2024 | target 2028 |
Other project Q574, Maricopa County Other |
220 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Solar + storage project 173, Greenlee County Solar + storage |
200 MW | In study |
Greenlee, AZ | West |
Jun 2024 | target 2028 |
Other project Q554, Pinal County Other |
200 MW | In study |
Pinal, AZ | West |
May 2024 | target 2030 |
Other project Q568, Yuma County Other |
200 MW | In study |
Yuma, AZ | West |
May 2024 | target 2028 |
Gas project 2024-G2, Mohave County Gas |
200 MW | In study |
Mohave, AZ | West |
Feb 2024 | target 2027 |
Other project Q573, Pinal County Other |
200 MW | In study |
Pinal, AZ | West |
May 2024 | target 2028 |
Other project Q565, Coconino County Other |
161 MW | In study |
Coconino, AZ | West |
May 2024 | target 2025 |
Other project Q548, Pinal County Other |
145 MW | In study |
Pinal, AZ | West |
Apr 2024 | target 2027 |
Other project Q559, Maricopa County Other |
80.0 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Other project Q557, Navajo County Other |
75.0 MW | In study |
Navajo, AZ | West |
May 2024 | target 2026 |
Gas project 2024-G6, Mohave County Gas |
50.0 MW | In study |
Mohave, AZ | West |
Aug 2024 | target 2027 |
Solar + storage project 2024-G1, Mohave County Solar + storage |
50.0 MW | In study |
Mohave, AZ | West |
Jan 2024 | target 2027 |
Other project Q550, Maricopa County Other |
43.0 MW | In study |
Maricopa, AZ | West |
Apr 2024 | target 2028 |
Other project Q549, Maricopa County Other |
42.1 MW | In study |
Maricopa, AZ | West |
Apr 2024 | target 2026 |