Interconnection queue in Arizona (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3254 MW
Active in queue254 MW3 requests
Agreement signed20.0 MW1 requests
Withdrawn305,612 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q239, Pinal County
Solar + storage
214 MWIn study Pinal, AZWest Mar 2016target 2021
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021
Agua Caliente Solar 2
Solar
20.0 MWIn study Maricopa, AZCAISO Mar 2016target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)