Projects with signed interconnection agreements in Arizona

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown179,849 MW
Active in queue108.6 GW281 requests
Agreement signed9,849 MW17 requests
Withdrawn699198.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Atlas Complex
Solar + storage
4,357 MWAgreement signed La Paz, AZCAISO May 2017target 2026
Solar + storage project Q275, Navajo County
Solar + storage
1,000 MWAgreement signed Navajo, AZWest Mar 2018target 2020
Centennial Flats
Solar + storage
767 MWAgreement signed La Paz, AZCAISO Apr 2018target 2026
Solar + storage project Q360, Maricopa County
Solar + storage
550 MWAgreement signed Maricopa, AZWest Sep 2020target 2023
Ironwood Solar
Solar + storage
500 MWAgreement signed Yuma, AZCAISO May 2017target 2026
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
White Wing Ranch Solar
Solar + storage
400 MWAgreement signed Yuma, AZCAISO Apr 2014target 2026
Dateland Energy Complex
Solar + storage
350 MWAgreement signed Yuma, AZCAISO Apr 2020target 2027
Battery storage project Q280, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Sep 2018target 2022
Battery storage project Q375, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Mar 2021target 2023
Solar + storage project Q295, Pinal County
Solar + storage
250 MWAgreement signed Pinal, AZWest Mar 2019target 2022
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Solar + storage project Q264, Pinal County
Solar + storage
130 MWAgreement signed Pinal, AZWest Sep 2017target 2021
Saddle Mountain Solar
Solar
125 MWAgreement signed Maricopa, AZCAISO Apr 2020target 2025
Battery storage project Q358, Maricopa County
Battery storage
100 MWAgreement signed Maricopa, AZWest Sep 2020target 2024
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)