United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Alabama (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown384,841 MW
Active in queue2,181 MW11 requests
Agreement signed310 MW3 requests
Withdrawn384,841 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project IC-1218, Lee County
Gas
640 MWWithdrawn / abandoned Lee, ALSoutheast Dec 2023
Solar project 601, Monroe County
Solar
240 MWWithdrawn / abandoned Monroe, ALSoutheast Dec 2023
Solar project IC-1164, Mobile County
Solar
200 MWWithdrawn / abandoned Mobile, ALSoutheast Aug 2023target 2027
Battery storage project IC-1175, Etowah County
Battery storage
200 MWWithdrawn / abandoned Etowah, ALSoutheast Sep 2023target 2027
Solar + storage project IC-1173, Talladega County
Solar + storage
200 MWWithdrawn / abandoned Talladega, ALSoutheast Sep 2023target 2026
Solar + storage project IC-1169, Lowndes County
Solar + storage
200 MWWithdrawn / abandoned Lowndes, ALSoutheast Aug 2023target 2027
Solar project IC-1212, Perry County
Solar
199 MWWithdrawn / abandoned Perry, ALSoutheast Dec 2023
Solar project 563, Franklin County
Solar
198 MWWithdrawn / abandoned Franklin, ALSoutheast Jun 2023
Solar project IC-1178, Baldwin County
Solar
160 MWWithdrawn / abandoned Baldwin, ALSoutheast Sep 2023target 2030
Solar project IC-1118, Houston County
Solar
150 MWWithdrawn / abandoned Houston, ALSoutheast Feb 2023
Solar project 576, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast Jul 2023target 2025
Solar + storage project IC-1182, Lowndes County
Solar + storage
138 MWWithdrawn / abandoned Lowndes, ALSoutheast Oct 2023target 2027
Solar project IC-1213, Perry County
Solar
136 MWWithdrawn / abandoned Perry, ALSoutheast Dec 2023
Solar project IC-1208, Lowndes County
Solar
120 MWWithdrawn / abandoned Lowndes, ALSoutheast Dec 2023target 2027
Solar project 591, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2023target 2025
Solar project 580, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Jul 2023target 2025
Solar + storage project IC-1171, Greene County
Solar + storage
80.0 MWWithdrawn / abandoned Greene, ALSoutheast Sep 2023
Solar project IC-1131, Blount County
Solar
80.0 MWWithdrawn / abandoned Blount, ALSoutheast Mar 2023
Solar + storage project IC-1109, Mobile County
Solar + storage
80.0 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2023target 2027
Solar + storage project IC-1110, Mobile County
Solar + storage
80.0 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2023
Solar + storage project IC-1151, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jul 2023target 2027
Solar + storage project IC-1111, Mobile County
Solar + storage
80.0 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2023
Solar project IC-1105, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar + storage project IC-1154, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jul 2023target 2028
Solar project IC-1106, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-1108, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-1135, Washington County
Solar
80.0 MWWithdrawn / abandoned Washington, ALSoutheast Apr 2023
Solar project IC-1157, Wilcox County
Solar
80.0 MWWithdrawn / abandoned Wilcox, ALSoutheast Jul 2023target 2028
Solar project IC-1104, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-1107, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar + storage project IC-1150, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jul 2023
Solar + storage project IC-1125, Perry County
Solar + storage
79.9 MWWithdrawn / abandoned Perry, ALSoutheast Mar 2023
Solar project IC-1124, Montgomery County
Solar
79.9 MWWithdrawn / abandoned Montgomery, ALSoutheast Mar 2023
Solar project IC-1123, Montgomery County
Solar
79.9 MWWithdrawn / abandoned Montgomery, ALSoutheast Mar 2023
Solar + storage project IC-1126, Perry County
Solar + storage
79.9 MWWithdrawn / abandoned Perry, ALSoutheast Mar 2023
Solar project IC-1133, Baldwin County
Solar
73.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Mar 2023target 2026
Solar + storage project 595, Blount County
Solar + storage
60.0 MWWithdrawn / abandoned Blount, ALSoutheast Dec 2023
Solar project 578, Colbert County
Solar
57.0 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)