United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Alabama (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown387,006 MW
Active in queue731 MW5 requests
Agreement signed571 MW3 requests
Withdrawn387,006 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project IC-772, Tallapoosa County
Gas
661 MWWithdrawn / abandoned Tallapoosa, ALSoutheast Feb 2019
Gas project 404, Colbert County
Gas
593 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar project 383, Lawrence County
Solar
500 MWWithdrawn / abandoned Lawrence, ALSoutheast Jul 2019
Solar project 382, Lawrence County
Solar
500 MWWithdrawn / abandoned Lawrence, ALSoutheast Jul 2019
Solar project 370, Colbert County
Solar
227 MWWithdrawn / abandoned Colbert, ALSoutheast May 2019
Solar + storage project IC-815, Henry County
Solar + storage
220 MWWithdrawn / abandoned Henry, ALSoutheast Oct 2019
Solar project IC-816, Geneva County
Solar
220 MWWithdrawn / abandoned Geneva, ALSoutheast Oct 2019
Solar + storage project IC-808, Autauga County
Solar + storage
220 MWWithdrawn / abandoned Autauga, ALSoutheast Oct 2019
Solar + storage project IC-811, Houston County
Solar + storage
220 MWWithdrawn / abandoned Houston, ALSoutheast Oct 2019
Solar + storage project IC-813, Pickens County
Solar + storage
220 MWWithdrawn / abandoned Pickens, ALSoutheast Oct 2019
Solar project IC-814, Marengo County
Solar
220 MWWithdrawn / abandoned Marengo, ALSoutheast Oct 2019
Solar + storage project IC-812, Montgomery County
Solar + storage
220 MWWithdrawn / abandoned Montgomery, ALSoutheast Oct 2019
Solar project IC-817, Dallas County
Solar
220 MWWithdrawn / abandoned Dallas, ALSoutheast Oct 2019
Solar + storage project IC-818, Houston County
Solar + storage
220 MWWithdrawn / abandoned Houston, ALSoutheast Oct 2019
Solar project 408, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar project IC-795, Hale County
Solar
200 MWWithdrawn / abandoned Hale, ALSoutheast May 2019
Solar project 386, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2019
Solar project 409, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar project 410, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar project 354, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast May 2019
Solar project IC-804, Marengo County
Solar
100 MWWithdrawn / abandoned Marengo, ALSoutheast Sep 2019target 2022
Solar + storage project IC-841, Washington County
Solar + storage
100 MWWithdrawn / abandoned Washington, ALSoutheast Dec 2019
Solar project 376, Lauderdale County
Solar
100 MWWithdrawn / abandoned Lauderdale, ALSoutheast Jun 2019
Solar + storage project IC-785, Calhoun County
Solar + storage
80.0 MWWithdrawn / abandoned Calhoun, ALSoutheast Mar 2019
Solar + storage project IC-783, Clarke County
Solar + storage
80.0 MWWithdrawn / abandoned Clarke, ALSoutheast Mar 2019
Solar project IC-780, Sumter County
Solar
80.0 MWWithdrawn / abandoned Sumter, ALSoutheast Mar 2019
Solar + storage project IC-837, Shelby County
Solar + storage
80.0 MWWithdrawn / abandoned Shelby, ALSoutheast Nov 2019
Solar + storage project IC-838, Shelby County
Solar + storage
80.0 MWWithdrawn / abandoned Shelby, ALSoutheast Nov 2019
Solar + storage project IC-782, Clarke County
Solar + storage
80.0 MWWithdrawn / abandoned Clarke, ALSoutheast Mar 2019
Solar project 357, Jackson County
Solar
80.0 MWWithdrawn / abandoned Jackson, ALSoutheast Jan 2019
Solar project IC-801, Washington County
Solar
80.0 MWWithdrawn / abandoned Washington, ALSoutheast Aug 2019
Solar project IC-788, Elmore County
Solar
80.0 MWWithdrawn / abandoned Elmore, ALSoutheast Apr 2019
Solar project IC-781, Sumter County
Solar
80.0 MWWithdrawn / abandoned Sumter, ALSoutheast Mar 2019
Solar project IC-784, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Mar 2019
Solar project IC-796, Dale County
Solar
79.8 MWWithdrawn / abandoned Dale, ALSoutheast Jun 2019
Solar project 394, Lawrence County
Solar
66.0 MWWithdrawn / abandoned Lawrence, ALSoutheast Aug 2019
Solar project IC-793, Mobile County
Solar
60.0 MWWithdrawn / abandoned Mobile, ALSoutheast May 2019
Solar project 365, Lauderdale County
Solar
59.0 MWWithdrawn / abandoned Lauderdale, ALSoutheast Apr 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)