United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Arizona, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25985.6 GW
Active in queue85.6 GW259 requests
Agreement signed3,350 MW11 requests
Withdrawn650167.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

259 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q2409, Navajo County
Solar + storage
2,626 MWIn study Navajo, AZWest Feb 2024target 2028
Solar + storage project Q255, Coconino County
Solar + storage
2,000 MWIn study Coconino, AZWest May 2017target 2021
Battery storage project Q2405, Maricopa County
Battery storage
1,020 MWIn study Maricopa, AZWest Feb 2024target 2033
Other project Q617, Mohave County
Other
1,000 MWIn study Mohave, AZWest May 2025target 2031
Battery storage project Q468, Maricopa County
Battery storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Solar + storage project Q474, Maricopa County
Solar + storage
1,000 MWIn study Maricopa, AZWest Mar 2022target 2025
Solar + storage project Q379, Maricopa County
Solar + storage
1,000 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Solar + storage project Q275, Navajo County
Solar + storage
1,000 MWAgreement signed Navajo, AZWest Mar 2018target 2020
Solar project Q274, Coconino County
Solar
1,000 MWIn study Coconino, AZWest Mar 2018target 2024
Solar + storage project Q466, Yuma County
Solar + storage
1,000 MWIn study Yuma, AZWest Mar 2022target 2025
Solar + storage project 125, Apache County
Solar + storage
1,000 MWIn study Apache, AZWest Jun 2022target 2025
Gas project Q32, Pinal County
Gas
928 MWIn study Pinal, AZWest Aug 2023target 2026
Solar + storage project Q2417, Maricopa County
Solar + storage
843 MWIn study Maricopa, AZWest Feb 2024target 2028
Solar + storage project Q2412, Navajo County
Solar + storage
822 MWIn study Navajo, AZWest Feb 2024target 2028
Gas project 174, Pima County
Gas
800 MWIn study Pima, AZWest Jun 2024target 2027
Solar + storage project Q38, Maricopa County
Solar + storage
800 MWIn study Maricopa, AZWest Feb 2023target 2027
Other project 103, Apache County
Other
768 MWIn study Apache, AZWest Nov 2021target 2024
Solar + storage project Q402, Navajo County
Solar + storage
750 MWIn study Navajo, AZWest Sep 2021target 2025
Solar + storage project Q317, Coconino County
Solar + storage
750 MWIn study Coconino, AZWest Sep 2019target 2023
Solar + storage project Q2515, Maricopa County
Solar + storage
718 MWIn study Maricopa, AZWest Feb 2025target 2028
Solar + storage project Q401, Coconino County
Solar + storage
700 MWIn study Coconino, AZWest Sep 2021target 2026
Solar + storage project 93, Apache County
Solar + storage
700 MWIn study Apache, AZWest Apr 2021target 2021
Solar + storage project Q488, Maricopa County
Solar + storage
600 MWIn study Maricopa, AZWest Sep 2022target 2026
Solar + storage project 2023-MP2, Mohave County
Solar + storage
600 MWIn study Mohave, AZWest Mar 2023target 2026
Solar + storage project Q2415, Maricopa County
Solar + storage
600 MWIn study Maricopa, AZWest Feb 2024target 2028
Solar + storage project 90, Pima County
Solar + storage
600 MWIn study Pima, AZWest Jan 2021target 2025
Other project Q561, Maricopa County
Other
600 MWIn study Maricopa, AZWest May 2024target 2029
Solar + storage project Q387, Navajo County
Solar + storage
588 MWIn study Navajo, AZWest Mar 2021target 2025
Solar + storage project Q2406, Maricopa County
Solar + storage
565 MWIn study Maricopa, AZWest Feb 2024target 2029
Other project 2024-G4, Mohave County
Other
550 MWIn study Mohave, AZWest Apr 2024target 2027
Solar + storage project Q360, Maricopa County
Solar + storage
550 MWAgreement signed Maricopa, AZWest Sep 2020target 2023
Other project Q591, Maricopa County
Other
535 MWIn study Maricopa, AZWest May 2025target 2030
Battery storage project Q2512, Maricopa County
Battery storage
503 MWIn study Maricopa, AZWest Feb 2025target 2030
Solar + storage project Q29, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Jun 2021target 2027
Other project Q580, Maricopa County
Other
500 MWIn study Maricopa, AZWest May 2025target 2032
Wind + storage project Q311, Navajo County
Wind + storage
500 MWIn study Navajo, AZWest Sep 2019target 2021
Solar + storage project Q334, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Mar 2020target 2023
Other project Q616, Maricopa County
Other
500 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project 2023-MP1, Yavapai County
Solar + storage
500 MWIn study Yavapai, AZWest Feb 2023target 2026
Solar + storage project 84, Pima County
Solar + storage
500 MWIn study Pima, AZWest Sep 2020target 2023
Other project Q564, Maricopa County
Other
500 MWIn study Maricopa, AZWest May 2024target 2028
Onshore wind project NC5-008, Mohave County
Onshore wind
500 MWIn study Mohave, AZWest May 2021target 2025
Solar + storage project Q563, Pinal County
Solar + storage
500 MWIn study Pinal, AZWest May 2024target 2028
Solar + storage project Q28, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Oct 2019target 2027
Other project Q603, Yuma County
Other
500 MWIn study Yuma, AZWest May 2025target 2030
Battery storage project 2023-G16, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Dec 2023target 2028
Battery storage project 2023-G15, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Dec 2023target 2028
Solar + storage project Q393, Coconino County
Solar + storage
500 MWIn study Coconino, AZWest Mar 2021target 2024
Battery storage project 2024-MP2, Mohave County
Battery storage
500 MWIn study Mohave, AZWest Jan 2024target 2028
Other project Q599, Yuma County
Other
500 MWIn study Yuma, AZWest May 2025target 2031
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)