Requests shown7788 MW
Active in queue2,381 MW21 requests
Agreement signed788 MW7 requests
Withdrawn24828.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-695, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project IC-696, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Solar project IC-768, Dodge County
Solar
120 MWAgreement signed Dodge, GASoutheast Dec 2018target 2027
Solar project IC-769, Oglethorpe County
Solar
60.0 MWAgreement signed Oglethorpe, GASoutheast Dec 2018target 2023
Solar project IC-759, Burke County
Solar
40.0 MWAgreement signed Burke, GASoutheast Dec 2018target 2023
Solar project IC-762, Oglethorpe County
Solar
38.0 MWAgreement signed Oglethorpe, GASoutheast Dec 2018target 2023
Solar project 337, Lake County
Solar
30.0 MWAgreement signed Lake, TNSoutheast Jan 2018target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)