United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in SPP (Southwest Power Pool) (2014 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown182,031 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn568,704 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2014-040, Castro County
Onshore wind
320 MWOperating Castro, TXSPP Sep 20142016
Onshore wind project GEN-2014-021, Atchison County
Onshore wind
300 MWOperating Atchison, MOSPP Sep 20142017
Onshore wind project GEN-2014-056, Canadian County
Onshore wind
250 MWOperating Canadian, OKSPP Sep 20142018
Onshore wind project GEN-2014-057, Grady County
Onshore wind
250 MWOperating Grady, OKSPP Sep 20142016
Onshore wind project GEN-2014-064, Garfield County
Onshore wind
248 MWOperating Garfield, OKSPP Sep 20142018
Onshore wind project GEN-2014-001, Marion County
Onshore wind
201 MWOperating Marion, KSSPP Jan 20142023
Onshore wind project GEN-2014-020, Grady County
Onshore wind
100 MWOperating Grady, OKSPP Jul 20142017
Onshore wind project GEN-2014-013, Antelope County
Onshore wind
73.5 MWOperating Antelope, NESPP Mar 20142015
Solar project GEN-2014-034, Chaves County
Solar
70.0 MWOperating Chaves, NMSPP Sep 20142016
Solar project GEN-2014-033, Chaves County
Solar
70.0 MWOperating Chaves, NMSPP Sep 20142016
Gas project GEN-2014-028, Cherokee County
Gas
50.0 MWOperating Cherokee, KSSPP Sep 20142016
Onshore wind project GEN-2014-031, Antelope County
Onshore wind
35.8 MWOperating Antelope, NESPP Sep 20142016
Solar project GEN-2014-035, Chaves County
Solar
30.0 MWOperating Chaves, NMSPP Sep 20142023
Onshore wind project GEN-2014-002, Dewey County
Onshore wind
10.5 MWOperating Dewey, OKSPP Feb 20142015
Onshore wind project GEN-2014-032, Antelope County
Onshore wind
10.2 MWOperating Antelope, NESPP Sep 20142014
Onshore wind project GEN-2014-005, Caddo County
Onshore wind
5.7 MWOperating Caddo, OKSPP Feb 20142015
Onshore wind project GEN-2014-004, Jefferson County
Onshore wind
4.0 MWOperating Jefferson, NESPP Feb 20142013
Onshore wind project GEN-2014-025, Rush County
Onshore wind
2.4 MWOperating Rush, KSSPP Sep 20142015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)