Completed queue projects in Oklahoma, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9615.0 GW
Active in queue50.1 GW232 requests
Agreement signed13.3 GW77 requests
Withdrawn45299.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

96 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2013-028, Mayes County
Gas
538 MWOperating Mayes, OKSPP Sep 20132017
Onshore wind project GEN-2016-045, Cimarron County
Onshore wind
499 MWOperating Cimarron, OKSPP Mar 20162022
Onshore wind project GEN-2016-057, Cimarron County
Onshore wind
499 MWOperating Cimarron, OKSPP Mar 20162022
Onshore wind project GEN-2007-062, Harper County
Onshore wind
424 MWOperating Harper, OKSPP Dec 20072016
Onshore wind project GEN-2016-091, Caddo County
Onshore wind
304 MWOperating Caddo, OKSPP Oct 20162022
Onshore wind project GEN-2015-036, Johnston County
Onshore wind
304 MWOperating Johnston, OKSPP Sep 20152020
Onshore wind project GEN-2015-047, Noble County
Onshore wind
300 MWOperating Noble, OKSPP Oct 20152018
Onshore wind project GEN-2016-037, Washita County
Onshore wind
300 MWOperating Washita, OKSPP Mar 20162023
Onshore wind project GEN-2011-054, Canadian County
Onshore wind
300 MWOperating Canadian, OKSPP Sep 20112014
Onshore wind project GEN-2010-001, Beaver County
Onshore wind
300 MWOperating Beaver, OKSPP Mar 20102015
Onshore wind project GEN-2008-013, Garfield County
Onshore wind
300 MWOperating Garfield, OKSPP Feb 20082012
Onshore wind project GEN-2010-040, Canadian County
Onshore wind
300 MWOperating Canadian, OKSPP Aug 20102012
Onshore wind project GEN-2015-063, Kingfisher County
Onshore wind
300 MWOperating Kingfisher, OKSPP Oct 20152018
Onshore wind project GEN-2007-044, Blaine County
Onshore wind
299 MWOperating Blaine, OKSPP Oct 20072014
Onshore wind project GEN-2013-029, Grant County
Onshore wind
299 MWOperating Grant, OKSPP Sep 20132016
Onshore wind project GEN-2012-032, Kay County
Onshore wind
299 MWOperating Kay, OKSPP Sep 20122015
Onshore wind project GEN-2016-118, Kingfisher County
Onshore wind
288 MWOperating Kingfisher, OKSPP Nov 20162021
Onshore wind project GEN-2008-047, Beaver County
Onshore wind
263 MWOperating Beaver, OKSPP May 20082014
Onshore wind project GEN-2016-061, Garfield County
Onshore wind
251 MWOperating Garfield, OKSPP Mar 20162020
Onshore wind project GEN-2014-056, Canadian County
Onshore wind
250 MWOperating Canadian, OKSPP Sep 20142018
Onshore wind project GEN-2016-068, Garfield County
Onshore wind
250 MWOperating Garfield, OKSPP Mar 20162020
Onshore wind project GEN-2014-057, Grady County
Onshore wind
250 MWOperating Grady, OKSPP Sep 20142016
Onshore wind project GEN-2014-064, Garfield County
Onshore wind
248 MWOperating Garfield, OKSPP Sep 20142018
Onshore wind project GEN-2016-003, Ellis County
Onshore wind
248 MWOperating Ellis, OKSPP Mar 20162022
Onshore wind project GEN-2016-032, Kingfisher County
Onshore wind
200 MWOperating Kingfisher, OKSPP Mar 20162024
Onshore wind project GEN-2007-043, Grady County
Onshore wind
200 MWOperating Grady, OKSPP Oct 20072010
Onshore wind project GEN-2015-001, Kay County
Onshore wind
200 MWOperating Kay, OKSPP Mar 20152016
Onshore wind project GEN-2015-034, Kay County
Onshore wind
200 MWOperating Kay, OKSPP Aug 20152020
Onshore wind project GEN-2015-048, Major County
Onshore wind
200 MWOperating Major, OKSPP Oct 20152021
Onshore wind project GEN-2016-095, Caddo County
Onshore wind
200 MWOperating Caddo, OKSPP Dec 20202024
Onshore wind project GEN-2007-046, Texas County
Onshore wind
200 MWOperating Texas, OKSPP Oct 20072015
Onshore wind project GEN-2015-082, Beaver County
Onshore wind
200 MWOperating Beaver, OKSPP Sep 20152020
Onshore wind project GEN-2007-021, Dewey County
Onshore wind
199 MWOperating Dewey, OKSPP May 20072014
Onshore wind project GEN-2011-014, Beaver County
Onshore wind
198 MWOperating Beaver, OKSPP Mar 20112016
Onshore wind project GEN-2008-044, Dewey County
Onshore wind
198 MWOperating Dewey, OKSPP May 20082012
Gas project GEN-2005-024, Tulsa County
Gas
181 MWOperating Tulsa, OKSPP Dec 20052007
Gas project GEN-2005-022, Caddo County
Gas
177 MWOperating Caddo, OKSPP Dec 20052007
Onshore wind project GEN-2016-126, Murray County
Onshore wind
173 MWOperating Murray, OKSPP Nov 20162021
Onshore wind project GEN-2015-015, Grant County
Onshore wind
155 MWOperating Grant, OKSPP Mar 20152017
Onshore wind project GEN-2007-050, Woodward County
Onshore wind
152 MWOperating Woodward, OKSPP Oct 20072010
Onshore wind project GEN-2016-022, Kay County
Onshore wind
152 MWOperating Kay, OKSPP Mar 20162020
Onshore wind project GEN-2008-023, Washita County
Onshore wind
150 MWOperating Washita, OKSPP Mar 20082012
Gas project GEN-2007-052, Caddo County
Gas
150 MWOperating Caddo, OKSPP Nov 20072009
Onshore wind project GEN-2016-020, Woodward County
Onshore wind
148 MWOperating Woodward, OKSPP Apr 20162020
Gas project GEN-2013-012, Logan County
Gas
147 MWOperating Logan, OKSPP Mar 20132014
Onshore wind project GEN-2017-027, Carter County
Onshore wind
140 MWOperating Carter, OKSPP May 20172021
Onshore wind project GEN-2006-035, Beckham County
Onshore wind
132 MWOperating Beckham, OKSPP Aug 20062012
Onshore wind project GEN-2006-046, Dewey County
Onshore wind
130 MWOperating Dewey, OKSPP Dec 20062011
Onshore wind project GEN-2002-005, Roger Mills County
Onshore wind
123 MWOperating Roger Mills, OKSPP Apr 20022008
Gas project GEN-2012-041, Kay County
Gas
122 MWOperating Kay, OKSPP Sep 20122015
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)