United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in New Mexico, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown121,844 MW
Active in queue10.3 GW47 requests
Agreement signed1,566 MW8 requests
Withdrawn14529.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2006-026, Lea County
Gas
604 MWOperating Lea, NMSPP Jul 20062008
Onshore wind project GEN-2008-022, Chaves County
Onshore wind
300 MWOperating Chaves, NMSPP Mar 20082015
Onshore wind project GEN-2016-123, Roosevelt County
Onshore wind
298 MWOperating Roosevelt, NMSPP Nov 20162020
Onshore wind project GEN-2016-124, Roosevelt County
Onshore wind
150 MWOperating Roosevelt, NMSPP Nov 20162020
Onshore wind project GEN-2001-033, Chaves County
Onshore wind
120 MWOperating Chaves, NMSPP Sep 20012005
Onshore wind project GEN-2023-GR3, Quay County
Onshore wind
80.0 MWOperating Quay, NMSPP Jun 20232024
Onshore wind project GEN-2016-125, Roosevelt County
Onshore wind
74.0 MWOperating Roosevelt, NMSPP Nov 20162020
Solar project GEN-2014-034, Chaves County
Solar
70.0 MWOperating Chaves, NMSPP Sep 20142016
Solar project GEN-2014-033, Chaves County
Solar
70.0 MWOperating Chaves, NMSPP Sep 20142016
Solar project GEN-2014-035, Chaves County
Solar
30.0 MWOperating Chaves, NMSPP Sep 20142023
Solar project GEN-2013-022, Quay County
Solar
25.0 MWOperating Quay, NMSPP Sep 20132016
Gas project GEN-2011-046, Quay County
Gas
23.0 MWOperating Quay, NMSPP Sep 20112013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)