United States βΊ Grid βΊ Interconnection queues βΊ New Mexico
OCTARY USA Β· INTERCONNECTION QUEUESCompleted queue projects in New Mexico, SPP
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project GEN-2006-026, Lea County Gas |
604 MW | |
| Onshore wind project GEN-2008-022, Chaves County Onshore wind |
300 MW | |
| Onshore wind project GEN-2016-123, Roosevelt County Onshore wind |
298 MW | |
| Onshore wind project GEN-2016-124, Roosevelt County Onshore wind |
150 MW | |
| Onshore wind project GEN-2001-033, Chaves County Onshore wind |
120 MW | |
| Onshore wind project GEN-2023-GR3, Quay County Onshore wind |
80.0 MW | |
| Onshore wind project GEN-2016-125, Roosevelt County Onshore wind |
74.0 MW | |
| Solar project GEN-2014-034, Chaves County Solar |
70.0 MW | |
| Solar project GEN-2014-033, Chaves County Solar |
70.0 MW | |
| Solar project GEN-2014-035, Chaves County Solar |
30.0 MW | |
| Solar project GEN-2013-022, Quay County Solar |
25.0 MW | |
| Gas project GEN-2011-046, Quay County Gas |
23.0 MW |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)