United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in PJM (Mid-Atlantic, Midwest)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8125 MW
Active in queue125 MW8 requests
Agreement signed50.0 MW1 requests
Withdrawn24416.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Mea Nug
Other
50.0 MWAgreement signed Monongalia, WVPJM Sep 2020target 2028
Alexandria
Other Β· Reworld REC LLC
20.0 MWIn study Arlington, VAPJM Feb 2025target 2020
Other project AH2-006, Pickaway County
Other
14.2 MWIn study Pickaway, OHPJM Oct 2021target 2024
Other project AH2-007, Fayette County
Other
10.1 MWIn study Fayette, OHPJM Oct 2021target 2024
Other project AH1-661, Muskingum County
Other Β· Tallgrass Muskingum Community Power, LLC
10.1 MWIn study Muskingum, OHPJM Feb 2025target 2023
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Other project AI1-053, Mercer County
Other
6.6 MWIn study Mercer, PAPJM Jun 2022target 2022
Other project AH2-001, Susquehanna County
Other
3.6 MWIn study Susquehanna, PAPJM Oct 2021target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)