United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Coal interconnection queue in PJM (Mid-Atlantic, Midwest)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown136.0 MW
Active in queue36.0 MW1 requests
Agreement signed36.0 MW1 requests
Withdrawn7035.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Mountaineer #1
Coal
36.0 MWAgreement signed WVPJM Oct 20152018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)