United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Kentucky, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10281 MW
Active in queue7,064 MW59 requests
Agreement signed1,592 MW15 requests
Withdrawn14718.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Bluebird Solar
Solar
80.0 MWOperating Harrison, KYPJM Sep 20162025
Turkey Creek Solar
Solar
50.0 MWOperating Garrard, KYPJM Mar 20192022
Glover Creek Solar
Solar
35.0 MWOperating Metcalfe, KYPJM Feb 20192024
Big Sandy #1
Gas
20.0 MWOperating Lawrence, KYPJM Jan 20072016
Bluebird Solar
Solar
20.0 MWOperating Harrison, KYPJM Feb 20172025
Glover Creek Solar
Solar
20.0 MWOperating Metcalfe, KYPJM Sep 20192024
Riverside Generating Stations
Gas
20.0 MWOperating Lawrence, KYPJM Oct 20102011
Big Sandy #1
Gas
17.0 MWOperating Lawrence, KYPJM Mar 20172016
Big Sandy #1
Gas
13.0 MWOperating Lawrence, KYPJM Aug 20162016
Riverside Generating Station
Gas
6.0 MWOperating Lawrence, KYPJM Aug 20122016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)