Interconnection queue in NYISO (New York) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13370 MW
Active in queue370 MW13 requests
Agreement signed0.0 MW0 requests
Withdrawn252,046 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Heritage Wind
Onshore wind Β· Heritage Wind, LLC
126 MWIn study Genesee, NYNYISO Sep 2016target 2026
Riverhead Solar 2
Solar Β· Riverhead Solar 2, LLC
36.0 MWIn study Suffolk, NYNYISO Feb 2016target 2027
Little Pond Solar
Solar Β· Little Pond Solar, LLC
20.0 MWIn study Orange, NYNYISO Sep 2016target 2027
Hills Solar
Solar Β· SunEast Hills Solar LLC
20.0 MWIn study Herkimer, NYNYISO Oct 2016target 2026
Dog Corners Solar
Solar Β· SunEast Dog Corners Solar LLC
20.0 MWIn study Cayuga, NYNYISO Nov 2016target 2026
Greene County 1
Solar Β· Hecate Energy Greene 1 LLC
20.0 MWIn study Greene, NYNYISO Sep 2016target 2027
Watkins Rd Solar
Solar Β· Watkins Road Solar NY LLC
20.0 MWIn study Herkimer, NYNYISO Nov 2016target 2027
Highview Solar
Solar Β· SunEast Highview Solar LLC
20.0 MWIn study Wyoming, NYNYISO Dec 2016target 2026
Niagara Solar
Solar Β· Niagara NY Solar LLC
20.0 MWIn study Wyoming, NYNYISO Dec 2016target 2026
Sky High Solar
Solar Β· Sky High Solar, LLC
20.0 MWIn study Onondaga, NYNYISO May 2016target 2026
Rock District Solar
Solar Β· Rock District Solar, LLC
20.0 MWIn study Schoharie, NYNYISO Jul 2016target 2027
Scipio Solar
Solar Β· Scipio Solar NY LLC
18.0 MWIn study Cayuga, NYNYISO Dec 2016target 2026
Greene County 2
Solar Β· Hecate Energy Greene 2 LLC
10.0 MWIn study Greene, NYNYISO Sep 2016target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)