United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in NYISO (New York) (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,963 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn101,963 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
CPV Valley II
Gas Β· CPV Valley, LLC
820 MWWithdrawn / abandoned Orange, NYNYISO Feb 2012
Bowline Gen. Station Unit #3
Gas Β· NRG Energy, Inc.
814 MWWithdrawn / abandoned Rockland, NYNYISO May 2012
South Pier Improvement
Gas Β· Astoria Generating Co.
95.5 MWWithdrawn / abandoned Kings, NYNYISO May 2012
Berrians East Replacement
Gas Β· NRG Berrians East Development, LLC
94.2 MWWithdrawn / abandoned Queens, NYNYISO Oct 2012
Paragon Wind
Onshore wind Β· Clipper Wind Power Development
79.9 MWWithdrawn / abandoned Steuben, NYNYISO May 2012
Troups Creek Wind
Onshore wind Β· Ridgeline Energy, LLC
32.0 MWWithdrawn / abandoned Steuben, NYNYISO Mar 2012
Dexter Solar
Solar Β· Enel Green Power North America
17.0 MWWithdrawn / abandoned Jefferson, NYNYISO Jul 2012
Seneca II Expansion
Other Β· Seneca Energy II, LLC
6.4 MWWithdrawn / abandoned Seneca, NYNYISO Apr 2012
Monroe County Mill Seat
Other Β· Monroe County
3.2 MWWithdrawn / abandoned Monroe, NYNYISO Mar 2012
Griffiss Technology Park
Gas Β· GUSC Energy, Inc.
0.9 MWWithdrawn / abandoned Oneida, NYNYISO Aug 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)