United States βΊ Grid βΊ Interconnection queues βΊ Texas
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Texas, MISO (2025 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project E0030, Jefferson County Gas Β· Entergy Texas, Inc. |
820 MW | In study |
| Gas project E0032, San Jacinto County Gas Β· Entergy Texas, Inc. |
478 MW | In study |
| Onshore wind project J3902, Jefferson County Onshore wind |
289 MW | In study |
| Solar + storage project J2689, Liberty County Solar + storage |
180 MW | In study |
| Battery storage project J4103, Trinity County Battery storage |
150 MW | In study |
| Solar project J4124, Trinity County Solar |
100 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)358 Β· 104.0 GW
- SPP (Southwest Power Pool)33 Β· 9,266 MW
- MISO (Midcontinent)6 Β· 2,017 MW
- West (non-ISO utilities)5 Β· 997 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)