Interconnection queue in North Dakota, MISO (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown82,122 MW
Active in queue2,122 MW8 requests
Agreement signed0.0 MW0 requests
Withdrawn1203 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J4105, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2028
Solar + storage project J4106, Cass County
Solar + storage
500 MWIn study Cass, NDMISO Oct 2025target 2027
Red Butte Wind
Onshore wind Β· Red Butte Wind, LLC
457 MWIn study Morton, NDMISO Aug 2025target 2028
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Surplus; J1588
Battery storage
200 MWIn study Cass, NDMISO Mar 2025target 2028
Solar + storage project J4170, Richland County
Solar + storage
172 MWIn study Richland, NDMISO Oct 2025target 2029
Solar project J4077, Emmons County
Solar
45.0 MWIn study Emmons, NDMISO Oct 2025target 2030
Solar project J4070, Emmons County
Solar
40.0 MWIn study Emmons, NDMISO Oct 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)