πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nevada, CAISO (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown53,562 MW
Active in queue3,562 MW5 requests
Agreement signed2,162 MW4 requests
Withdrawn41,485 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 2 Solar Farm
Solar + storage
1,400 MWIn study Clark, NVCAISO Apr 2019target 2029
Bonanza Peak Solar Farm
Solar + storage
641 MWAgreement signed Clark, NVCAISO Apr 2019target 2027
Bonanza Solar
Solar + storage
600 MWAgreement signed Clark, NVCAISO Apr 2019target 2028
Yellow Pine 3
Solar + storage
517 MWAgreement signed Clark, NVCAISO Apr 2019target 2026
Rough Hat Hybrid Solar
Solar + storage
404 MWAgreement signed Nye, NVCAISO Apr 2019target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)