United States β€Ί Grid β€Ί Interconnection queues β€Ί California

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in California, CAISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown16367.8 GW
Active in queue148.9 GW376 requests
Agreement signed81.1 GW213 requests
Withdrawn2,050551.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

163 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Muon
Solar + storage
2,339 MWIn study Fresno, CACAISO Apr 2023target 2028
Quark
Solar + storage
2,045 MWIn study Fresno, CACAISO Apr 2023target 2028
Ripple
Solar + storage
1,880 MWIn study Kings, CACAISO Apr 2023target 2031
Plum
Solar + storage
1,560 MWIn study Kings, CACAISO Apr 2021target 2031
Sunflower
Solar + storage
1,430 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Broadview
Solar + storage
1,308 MWIn study Fresno, CACAISO Apr 2023target 2028
Matterhorn
Other
1,218 MWIn study Riverside, CACAISO Apr 2023target 2029
Solstice B
Solar + storage
1,211 MWIn study Fresno, CACAISO Apr 2023target 2031
Aviation
Gas
1,200 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Pion
Battery storage
1,168 MWIn study Fresno, CACAISO Apr 2023target 2028
Solstice A
Solar + storage
1,111 MWIn study Fresno, CACAISO Apr 2023target 2031
Hillside Energy Storage
Battery storage
1,065 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Musketeers
Solar + storage
1,047 MWIn study Tulare, CACAISO Apr 2023target 2029
Crusade
Battery storage
1,029 MWIn study Orange, CACAISO Apr 2023target 2028
Lagoonez
Battery storage
1,029 MWIn study Los Angeles, CACAISO Apr 2023target 2028
Invictus
Solar + storage
860 MWIn study Riverside, CACAISO Apr 2021target 2029
Amanece
Solar + storage
836 MWIn study Stanislaus, CACAISO Apr 2023target 2029
Carissalito Creek
Solar + storage
832 MWIn study Merced, CACAISO Apr 2023target 2030
Artemis
Solar + storage
825 MWIn study Kern, CACAISO Apr 2021target 2029
Valley Sunlight Refinery
Solar + storage
821 MWIn study Kings, CACAISO Apr 2021target 2032
Maravillosa 2
Solar + storage
812 MWIn study Kern, CACAISO Apr 2023target 2029
Solsken
Solar + storage
809 MWIn study Tulare, CACAISO Apr 2021target 2033
Stable
Solar + storage
750 MWIn study Fresno, CACAISO Apr 2023target 2031
Sunglow
Solar + storage
744 MWIn study Kings, CACAISO Apr 2023target 2030
Sunrise Power Improvement
Gas
656 MWIn study Kern, CACAISO Apr 2020target 2024
Yuha Desert Battery Storage
Battery storage
633 MWIn study Imperial, CACAISO Apr 2021target 2031
Cherry Lane Hybrid
Solar + storage
621 MWIn study Kern, CACAISO Apr 2021target 2031
Sunvine
Solar + storage
614 MWIn study Kern, CACAISO Apr 2023target 2031
Maestro
Solar + storage
609 MWIn study Fresno, CACAISO Apr 2023target 2029
Duran
Gas
600 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Soleil Cantil
Solar + storage
597 MWIn study Kern, CACAISO Apr 2021target 2033
Sienna 3
Solar + storage
576 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Soledad Solar
Solar
562 MWIn study Kern, CACAISO Apr 2023target 2028
East Wonder
Solar + storage
556 MWIn study Kern, CACAISO Apr 2023target 2029
Sagebrush Energy Storage
Battery storage
528 MWIn study Kern, CACAISO Apr 2021target 2033
Summit Valley Energy Storage
Battery storage
519 MWIn study San Bernardino, CACAISO Apr 2023target 2032
Lupine Energy Center
Battery storage
518 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Chronos Energy Storage
Battery storage
517 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Yacht Rock
Battery storage
514 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Dove Cove
Battery storage
514 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Belterra Energy Storage
Battery storage
514 MWIn study Calaveras, CACAISO Apr 2023target 2028
Fontus
Battery storage
514 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Blue Star
Solar + storage
513 MWIn study Kings, CACAISO Apr 2023target 2029
Rosa Storage
Battery storage
512 MWIn study Ventura, CACAISO Apr 2021target 2034
Bolt
Solar + storage
509 MWIn study Fresno, CACAISO Apr 2023target 2031
Torbino Solar
Solar
507 MWIn study Kern, CACAISO Apr 2023target 2029
Galicia Storage
Battery storage
506 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Ambar Energy Storage
Battery storage
505 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Hawkins Solar Hybrid
Solar + storage
500 MWIn study Kern, CACAISO Apr 2020target 2027
Cantus
Solar + storage
499 MWIn study Merced, CACAISO Apr 2023target 2031
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)