United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 92

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 92 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AF2-131, York County
Solar
5.0 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Saltville-Holston 34.5kV Solar Facility
Solar
5.0 MWWithdrawn / abandoned Smyth, VAPJM Dec 2015target 2017
Solar project AH1-515A, Allegheny County
Solar
5.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2021target 2023
Solar project AG2-038, Venango County
Solar
5.0 MWWithdrawn / abandoned Venango, PAPJM Nov 2020target 2022
Mercersburg Road Solar
Solar
5.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2020target 2024
Solar project AG1-338, Bedford County
Solar
5.0 MWWithdrawn / abandoned Bedford, PAPJM Sep 2020target 2023
Solar project AH1-192, Northumberland County
Solar
5.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2023
Pulaski Community Solar
Solar
5.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
Solar + storage project AG1-340, Bedford County
Solar + storage
5.0 MWWithdrawn / abandoned Bedford, PAPJM Sep 2020target 2024
ASD Brick Plant PA2 Solar
Solar + storage
5.0 MWWithdrawn / abandoned Beaver, PAPJM Sep 2020target 2024
Solar project AE2-015, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Nov 2018target 2020
Solar project X2-062, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Jun 2011target 2012
Solar project W3-143, Warren County
Solar
5.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2012
Fishermen's Atlantic City Windfarm (FACW)
Offshore wind
5.0 MWWithdrawn / abandoned Cape May, NJPJM Jan 2011target 2019
Solar + storage project AH2-202, Hunterdon County
Solar + storage
5.0 MWWithdrawn / abandoned Hunterdon, NJPJM Mar 2022target 2025
1900 River Road
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Aug 2010target 2013
Other project N30, Franklin County
Other
5.0 MWWithdrawn / abandoned Franklin, PAPJM Jan 2005target 2007
Solar project AD2-118, Sussex County
Solar
5.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2018target 2020
Church
Solar
5.0 MWWithdrawn / abandoned Kent, MDPJM Apr 2014target 2019
Solar project AH1-193, Northumberland County
Solar
5.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2023
Solar project AC1-169, Will County
Solar
5.0 MWWithdrawn / abandoned Will, ILPJM Oct 2016target 2017
Solar project AE2-069, Burlington County
Solar
5.0 MWWithdrawn / abandoned Burlington, NJPJM Feb 2019target 2020
Solar + storage project AH2-254, Mercer County
Solar + storage
5.0 MWWithdrawn / abandoned Mercer, NJPJM Mar 2022target 2025
Solar project AG2-611, Wayne County
Solar
5.0 MWWithdrawn / abandoned Wayne, PAPJM Mar 2021target 2023
Solar project AF2-135, Somerset County
Solar
5.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2020target 2022
Johnson Matthey
Gas
5.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2011target 2012
Solar project AH1-498, Crawford County
Solar
5.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2021target 2024
Gas project AC1-066, Union County
Gas
5.0 MWWithdrawn / abandoned Union, NJPJM Sep 2016target 2017
Solar + storage project AH2-179
Solar + storage
5.0 MWWithdrawn / abandoned PJM Mar 2022target 2024
Hempfield CSG 1
Solar
5.0 MWWithdrawn / abandoned Westmoreland, PAPJM Sep 2020target 2022
Solar project AB2-123, Howard County
Solar
5.0 MWWithdrawn / abandoned Howard, MDPJM Apr 2016target 2017
Solar project AH1-023, Franklin County
Solar
5.0 MWWithdrawn / abandoned Franklin, PAPJM May 2021target 2022
Solar + storage project AI1-200, Lawrence County
Solar + storage
5.0 MWWithdrawn / abandoned Lawrence, PAPJM Sep 2022target 2024
Solar project AH2-134, Kanawha County
Solar
5.0 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2022target 2023
Solar project AH1-512
Solar
5.0 MWWithdrawn / abandoned PJM Sep 2021target 2023
Other project K17, Greene County
Other
5.0 MWWithdrawn / abandoned Greene, PAPJM Jul 2003target 2004
Solar project AA2-037, Caroline County
Solar
5.0 MWWithdrawn / abandoned Caroline, MDPJM Jan 2015target 2015
Solar project AG2-496, Madison County
Solar
5.0 MWWithdrawn / abandoned Madison, OHPJM Mar 2021target 2022
Solar project AG2-525, Cass County
Solar
5.0 MWWithdrawn / abandoned Cass, MIPJM Mar 2021target 2023
Hough Solar Farm
Solar
4.9 MWWithdrawn / abandoned Sussex, NJPJM Sep 2011target 2015
Solar + storage project AE2-106, Cumberland County
Solar + storage
4.9 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2019target 2020
Other project V1-015, Hancock County
Other
4.8 MWWithdrawn / abandoned Hancock, OHPJM Mar 2009target 2010
Other project V4-012, Berks County
Other
4.8 MWWithdrawn / abandoned Berks, PAPJM Nov 2009target 2012
Other project Y1-013, Harrison County
Other
4.8 MWWithdrawn / abandoned Harrison, WVPJM Feb 2012target 2013
Solar project X1-006, Warren County
Solar
4.8 MWWithdrawn / abandoned Warren, NJPJM Feb 2011target 2012
Other project V4-072, Franklin County
Other
4.8 MWWithdrawn / abandoned Franklin, PAPJM Jan 2010target 2012
Solar project AG2-435, York County
Solar
4.6 MWWithdrawn / abandoned York, PAPJM Mar 2021target 2023
Gas project V3-050, Middlesex County
Gas
4.6 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2009target 2011
West Deptford Solar
Solar
4.6 MWWithdrawn / abandoned Gloucester, NJPJM Apr 2010target 2012
Solar project AE2-336, Prince George's County
Solar
4.6 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2019target 2020
Page 92 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)