United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2013 requests) โ€” page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown46255.8 GW
Active in queue3,270 MW17 requests
Agreement signed1,371 MW10 requests
Withdrawn46255.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

462 requests ยท page 8 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Z1-076, Worcester County
Solar
14.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2018
Hydro project G0488, Gem County
Hydro
13.0 MWWithdrawn / abandoned Gem, IDWest May 2013target 2016
Black Oak Wind
Onshore wind ยท Black Oak Wind Farm, LLC
12.5 MWWithdrawn / abandoned Tompkins, NYNYISO Jan 2013
Geothermal project 517, Klamath County
Geothermal
12.0 MWWithdrawn / abandoned Klamath, ORWest Sep 2013target 2015
Solar project Y3-057, Charles County
Solar
12.0 MWWithdrawn / abandoned Charles, MDPJM Mar 2013target 2014
Offshore Wind
Offshore wind
12.0 MWWithdrawn / abandoned Lincoln, MEISO-NE Dec 2013target 2017
Milford Solar
Solar
12.0 MWWithdrawn / abandoned Kent, DEPJM Mar 2013target 2014
Other project 121, Osceola County
Other ยท Masked
11.8 MWWithdrawn / abandoned Osceola, FLSoutheast Jul 2013target 2014
Other project 128, Suwannee County
Other ยท Duke Energy Florida, LLC
11.7 MWWithdrawn / abandoned Suwannee, FLSoutheast Dec 2013target 2015
Other project 127, Lake County
Other ยท Masked
11.0 MWWithdrawn / abandoned Lake, FLSoutheast Oct 2013
Solar project SGI-PNM-2013-08, Bernalillo County
Solar
10.0 MWWithdrawn / abandoned Bernalillo, NMWest Nov 2013target 2015
Solar project Z1-125, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project 415, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Oct 2013
Solar project Z1-117, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project Z1-123, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project Z1-118, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project SGI-PNM-2013-06, Valencia Cty County
Solar
10.0 MWWithdrawn / abandoned Valencia Cty, NMWest Nov 2013target 2015
Solar project IC-294, Echols County
Solar
10.0 MWWithdrawn / abandoned Echols, GASoutheast Apr 2013
Solar project Z1-121, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project 534, Jefferson County
Solar
10.0 MWWithdrawn / abandoned Jefferson, ORWest Nov 2013target 2016
Solar project 416, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Oct 2013
Solar project Z1-124, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Battery storage project Y3-096, Lawrence County
Battery storage
10.0 MWWithdrawn / abandoned Lawrence, OHPJM Apr 2013target 2015
Solar project 420, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Nov 2013
Solar project 533, Jackson County
Solar
10.0 MWWithdrawn / abandoned Jackson, ORWest Nov 2013target 2016
Solar project Z1-120, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project 417, Malheur County
Solar
10.0 MWWithdrawn / abandoned Malheur, ORWest Oct 2013
Solar project Z1-119, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Gas project Y3-047, Essex County
Gas
10.0 MWWithdrawn / abandoned Essex, NJPJM Feb 2013target 2013
Solar project Z1-122, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project Z1-126, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project IC-299, Jeff Davis County
Solar
10.0 MWWithdrawn / abandoned Jeff Davis, GASoutheast May 2013
Other project Z2-004, Gloucester County
Other
10.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2013target 2014
Solar project Z1-077, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2018
Hydro project 167, Broadwater County
Hydro
9.8 MWWithdrawn / abandoned Broadwater, MTWest Nov 2013target 2016
Deming Solar Project
Solar ยท Deming Solar Project LLC
9.0 MWWithdrawn / abandoned Luna, NMWest Sep 2013target 2017
Solar project SGI-PNM-2013-01, Valencia County
Solar
9.0 MWWithdrawn / abandoned Valencia, NMWest May 2013target 2014
Recovery Road Solar Farm
Solar
7.1 MWWithdrawn / abandoned Burlington, NJPJM Nov 2013target 2018
Battery storage project Z1-094, Licking County
Battery storage
6.0 MWWithdrawn / abandoned Licking, OHPJM Oct 2013target 2018
Sunfish Solar Project
Solar
6.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2013target 2017
Other project 524, Salt Lake County
Other
6.0 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2013target 2015
Battery storage project Z1-095, Allen County
Battery storage
6.0 MWWithdrawn / abandoned Allen, OHPJM Oct 2013target 2014
Battery storage project Z1-093, Sandusky County
Battery storage
6.0 MWWithdrawn / abandoned Sandusky, OHPJM Oct 2013target 2014
Onshore wind project GEN-2013-004, Antelope County
Onshore wind
6.0 MWWithdrawn / abandoned Antelope, NESPP Mar 2013target 2014
Battery storage project Z1-063, Licking County
Battery storage
6.0 MWWithdrawn / abandoned Licking, OHPJM Sep 2013target 2016
Camden (Cinnaminson Solar) 26kV
Solar
6.0 MWWithdrawn / abandoned Burlington, NJPJM Jan 2013target 2015
Other project 523, Utah County
Other
6.0 MWWithdrawn / abandoned Utah, UTWest Oct 2013target 2015
Linden Generating Station
Gas
6.0 MWWithdrawn / abandoned Union, NJPJM Feb 20132015
Gas project Z1-114, York County
Gas
6.0 MWWithdrawn / abandoned York, PAPJM Oct 2013target 2015
Solar project Y3-101, Ocean County
Solar
5.7 MWWithdrawn / abandoned Ocean, NJPJM Apr 2013target 2014

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)