United States › Grid › Interconnection queues › Utah
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Utah — page 6
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project PIS069, Tooele County Solar + storage · PacifiCorp |
125 MW | Withdrawn / abandoned |
| Solar + storage project PIS067, Tooele County Solar + storage · PacifiCorp |
125 MW | Withdrawn / abandoned |
| Solar + storage project C4-070, Tooele County Solar + storage · PacifiCorp |
125 MW | Withdrawn / abandoned |
| Solar project PIS017, Emery County Solar · PacifiCorp |
125 MW | Withdrawn / abandoned |
| Solar project 1130, Iron County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project C3-061, San Juan County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project 1203, Iron County Solar |
120 MW | Withdrawn / abandoned |
| Solar project 1000, Weber County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project C2-160, Iron County Solar + storage |
115 MW | Withdrawn / abandoned |
| Geothermal project C1-05, Millard County Geothermal |
115 MW | Withdrawn / abandoned |
| Onshore wind project 74, Box Elder County Onshore wind |
115 MW | Withdrawn / abandoned |
| Battery storage project PIS039, Salt Lake County Battery storage |
110 MW | Withdrawn / abandoned |
| Battery storage project C2-164, Salt Lake County Battery storage |
110 MW | Withdrawn / abandoned |
| Onshore wind project 36, Iron County Onshore wind |
104 MW | Withdrawn / abandoned |
| Solar project 975, Juab County Solar |
101 MW | Withdrawn / abandoned |
| Solar project TCS-08, Juab County Solar |
101 MW | Withdrawn / abandoned |
| Solar + storage project 1036, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project C3-115, Salt Lake County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C3-134, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project 369, Iron County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project C4-077, Salt Lake County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 1035, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C1-30, Beaver County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C4-047, Millard County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project 981, Box Elder County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project C3-144, Box Elder County Solar + storage |
100 MW | Withdrawn / abandoned |
| Battery storage project C3-138, Kane County Battery storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project 35, Washington County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project 219-A, San Juan County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-206, Iron County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project 977, Box Elder County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project C4-078, Salt Lake County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 871, Juab County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 1056, Juab County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 1052, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-132, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C3-059, Duchesne County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C1-26, Carbon County Solar + storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project 291, Carbon/Utah County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project 811, Carbon County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project C2-126, Salt Lake County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C3-012, Emery County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C4-084, Duchesne County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project C1-33, San Juan County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-77, Box Elder County Solar + storage |
100 MW | Withdrawn / abandoned |
| Onshore wind project 219-B, San Juan County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar + storage project C2-113, Emery County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project C3-176, Duchesne County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 1051, Utah County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project 1218, Beaver County Solar + storage |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)