United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 53

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 53 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Pacific Winds Inc
Onshore wind · Pacific Winds, Inc.
100 MWWithdrawn / abandoned Benton, WAWest Mar 2001target 2002
100MW Midway-Bonneville
Onshore wind · ABB Equity Ventures Inc
100 MWWithdrawn / abandoned Klickitat, ORWest Jun 2001target 2003
Battery storage project S0001, Klamath County
Battery storage
100 MWWithdrawn / abandoned Klamath, ORWest Jul 2020target 2024
Solar project Company IB, Lander County
Solar
100 MWWithdrawn / abandoned Lander, NVWest Mar 2018target 2020
Battery storage project Q298, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2019target 2023
Battery storage project Q106, Los Angeles County
Battery storage
100 MWWithdrawn / abandoned Los Angeles, CAWest Jul 2023target 2026
Battery storage project Q419, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Sep 2021target 2024
Battery storage project 722, Canyon County
Battery storage
100 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Battery storage project IA-PNM-2023-23, Torrance County
Battery storage
100 MWWithdrawn / abandoned Torrance, NMWest Sep 2023target 2028
Onshore wind project 17-08212, Larimer County
Onshore wind
100 MWWithdrawn / abandoned Larimer, COWest Aug 2017target 2020
Onshore wind project 2008-G6
Onshore wind
100 MWWithdrawn / abandoned West Feb 2008target 2011
Solar project 2019-G6
Solar
100 MWWithdrawn / abandoned West May 2019target 2021
Battery storage project 22-108, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, ORWest Feb 2022target 2024
Battery storage project C4-078, Salt Lake County
Battery storage
100 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Solar project 2023-G5
Solar
100 MWWithdrawn / abandoned West Dec 2022target 2026
Solar project 715, Bingham County
Solar
100 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2027
Solar + storage project Company NF, Humbolt County
Solar + storage
100 MWWithdrawn / abandoned Humbolt, NVWest Mar 2022target 2025
Battery storage project Q520, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2026
Battery storage project Q470, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2026
Solar project 19-04261, Larimer County
Solar
100 MWWithdrawn / abandoned Larimer, COWest Apr 2019target 2021
Solar + storage project 871, Juab County
Solar + storage
100 MWWithdrawn / abandoned Juab, UTWest May 2017target 2020
Solar + storage project 1056, Juab County
Solar + storage
100 MWWithdrawn / abandoned Juab, UTWest Aug 2018target 2021
Solar + storage project 1052, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Onshore wind project 449, Stillwater County
Onshore wind
100 MWWithdrawn / abandoned Stillwater, MTWest Oct 2023target 2028
Gas project 23, Lane County
Gas
100 MWWithdrawn / abandoned Lane, ORWest Jun 2003target 2006
Onshore wind project GI-2008-17, Arapahoe County
Onshore wind
100 MWWithdrawn / abandoned Arapahoe, COWest Aug 2008target 2012
100MW Harvalum
Onshore wind · ABB Equity Ventures Inc
100 MWWithdrawn / abandoned Klickitat, WAWest Jun 2001target 2003
Solar project GI-2008-28, Saguache County
Solar
100 MWWithdrawn / abandoned Saguache, COWest Nov 2008target 2015
Onshore wind project GI-0506, Stanley County
Onshore wind
100 MWWithdrawn / abandoned Stanley, SDWest Jan 2005
Onshore wind project G0338, Umatilla County
Onshore wind
100 MWWithdrawn / abandoned Umatilla, ORWest Jul 2008target 2013
Battery storage project IA-PNM-2020-15, Bernalillo County
Battery storage
100 MWWithdrawn / abandoned Bernalillo, NMWest Sep 2020target 2023
Solar project 52, Adams County
Solar
100 MWWithdrawn / abandoned Adams, WAWest Feb 2017
Geothermal project 283, Twin Falls County
Geothermal
100 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2009target 2010
Iberdrola Renewables Inc
Onshore wind · Avangrid Power, LLC
100 MWWithdrawn / abandoned Gilliam, ORWest Sep 2002target 2003
Battery storage project 16-062, Marion County
Battery storage
100 MWWithdrawn / abandoned Marion, ORWest Sep 2016target 2019
Battery storage project 22-116, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, ORWest Oct 2022target 2024
Solar + storage project Q286, Yavapai County
Solar + storage
100 MWWithdrawn / abandoned Yavapai, AZWest Sep 2018target 2021
Solar + storage project Company JS, Pershing County
Solar + storage
100 MWWithdrawn / abandoned Pershing, NVWest Mar 2019target 2021
Battery storage project IA-PNM-2017-17, Santa Fe County
Battery storage
100 MWWithdrawn / abandoned Santa Fe, NMWest Oct 2017target 2020
Onshore wind project GI-0927, Mercer County
Onshore wind
100 MWWithdrawn / abandoned Mercer, NDWest Oct 2009target 2013
Onshore wind project 1131, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, WYWest Apr 2019target 2022
Solar + storage project 2017-G2, Contra Costa County
Solar + storage
100 MWWithdrawn / abandoned Contra Costa, CAWest Sep 2017target 2021
Solar + storage project Company KM, Nye County
Solar + storage
100 MWWithdrawn / abandoned Nye, NVWest Mar 2020target 2023
Battery storage project IA-PNM-2023-15, Roosevelt County
Battery storage
100 MWWithdrawn / abandoned Roosevelt, NMWest Sep 2023target 2028
Solar + storage project Q505, Pinal County
Solar + storage
100 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2026
Solar project GI-2014-11, Alamosa County
Solar
100 MWWithdrawn / abandoned Alamosa, COWest Nov 2014target 2016
Solar project Company 136, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Sep 2014target 2016
Solar + storage project Company OE, Humboldt County
Solar + storage
100 MWWithdrawn / abandoned Humboldt, NVWest Nov 2022target 2026
Battery storage project GI-SISS-2025-01, Kit Carson County
Battery storage
100 MWWithdrawn / abandoned Kit Carson, COWest Jun 2025target 2028
Solar + storage project C2-132, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest May 2022target 2026
Page 53 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)