Requests shown2,738603.3 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,738 requests · page 51 of 55
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-281, Echols County
Solar
20.0 MWWithdrawn / abandoned Echols, GASoutheast Feb 2013
Solar project IC-270, Early County
Solar
20.0 MWWithdrawn / abandoned Early, GASoutheast Oct 2012
Solar project IC-292, Laurens County
Solar
20.0 MWWithdrawn / abandoned Laurens, GASoutheast Apr 2013
Battery storage project 586, Wayne County
Battery storage
20.0 MWWithdrawn / abandoned Wayne, TNSoutheast Oct 2023target 2029
Solar project IC-302, Bartow County
Solar
20.0 MWWithdrawn / abandoned Bartow, GASoutheast Jun 2013
Other project 158, Campbell County
Other
20.0 MWWithdrawn / abandoned Campbell, TNSoutheast Apr 2001
Solar project 100, Aiken County
Solar
20.0 MWWithdrawn / abandoned Aiken, SCSoutheast Apr 2018target 2020
Solar project IC-376, Brooks County
Solar
20.0 MWWithdrawn / abandoned Brooks, GASoutheast Apr 2014
Solar project IC-628, Long County
Solar
20.0 MWWithdrawn / abandoned Long, GASoutheast Apr 2017
Solar project IC-300, Clay County
Solar
20.0 MWWithdrawn / abandoned Clay, GASoutheast May 2013
Solar project 268, Hardeman County
Solar
20.0 MWWithdrawn / abandoned Hardeman, TNSoutheast Apr 2015
Solar project 115, Hardee County
Solar · Masked
20.0 MWWithdrawn / abandoned Hardee, FLSoutheast Oct 2011target 2013
Solar project IC-301, Tattnall County
Solar
20.0 MWWithdrawn / abandoned Tattnall, GASoutheast Jun 2013
Solar project IC-477, Dooly County
Solar
20.0 MWWithdrawn / abandoned Dooly, GASoutheast Aug 2016
Solar project 188, Lake County
Solar · Masked
20.0 MWWithdrawn / abandoned Lake, FLSoutheast Jun 2017target 2019
Battery storage project 271, Polk County
Battery storage
20.0 MWWithdrawn / abandoned Polk, TNSoutheast Aug 2015
Solar project IC-296, Bulloch County
Solar
20.0 MWWithdrawn / abandoned Bulloch, GASoutheast May 2013
Solar project 565970, Wilkes County
Solar
20.0 MWWithdrawn / abandoned Wilkes, NCSoutheast Jun 2022
Solar project IC-359, Ben Hill County
Solar
20.0 MWWithdrawn / abandoned Ben Hill, GASoutheast Apr 2014
Solar project IC-358, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Apr 2014
Solar project IC-366, Lowndes County
Solar
20.0 MWWithdrawn / abandoned Lowndes, GASoutheast Apr 2014
Solar project IC-284, Bulloch County
Solar
20.0 MWWithdrawn / abandoned Bulloch, GASoutheast Mar 2013
Solar project 20230829003, Aiken County
Solar
20.0 MWWithdrawn / abandoned Aiken, SCSoutheast target 2026
Other project 160, Johnson County
Other
20.0 MWWithdrawn / abandoned Johnson, TNSoutheast May 2001
Solar project IC-350, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, GASoutheast Apr 2014
Solar project IC-289, Clay County
Solar
20.0 MWWithdrawn / abandoned Clay, GASoutheast Apr 2013
Solar project 962985, Chester County
Solar
20.0 MWWithdrawn / abandoned Chester, SCSoutheast Sep 2024
Solar project IC-310, Baker County
Solar
20.0 MWWithdrawn / abandoned Baker, GASoutheast Aug 2013
Solar project IC-545, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Nov 2016
Solar project 270, Crockett County
Solar
20.0 MWWithdrawn / abandoned Crockett, TNSoutheast May 2015
Solar project IC-547, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Nov 2016
Solar project IC-619, Mcintosh County
Solar
20.0 MWWithdrawn / abandoned Mcintosh, GASoutheast Apr 2017
Solar project 255, Marion County
Solar · Masked
20.0 MWWithdrawn / abandoned Marion, FLSoutheast May 2019target 2021
Solar project IC-285, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, GASoutheast Mar 2013
Solar project IC-626, Bleckley County
Solar
20.0 MWWithdrawn / abandoned Bleckley, GASoutheast Apr 2017
Solar project IC-383, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Jun 2014
Solar project 121, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Feb 2019
Solar project 116, Chesterfield County
Solar
19.9 MWWithdrawn / abandoned Chesterfield, SCSoutheast Oct 2018target 2019
Solar project 89, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Mar 2018
Solar project 115, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Oct 2018target 2019
Solar project 118, Marlboro County
Solar
19.9 MWWithdrawn / abandoned Marlboro, SCSoutheast Dec 2018target 2020
Solar project IC-635
Solar
19.8 MWWithdrawn / abandoned Southeast Apr 2017
Solar project IC-351, Bacon County
Solar
19.8 MWWithdrawn / abandoned Bacon, GASoutheast Apr 2014
Solar project IC-309, Peach County
Solar
19.8 MWWithdrawn / abandoned Peach, GASoutheast Jul 2013
Solar project IC-412, Hale County
Solar
19.7 MWWithdrawn / abandoned Hale, ALSoutheast Apr 2015
Solar project IC-417, Dallas County
Solar
19.7 MWWithdrawn / abandoned Dallas, ALSoutheast Aug 2015
Solar project IC-402, Berrien County
Solar
19.7 MWWithdrawn / abandoned Berrien, GASoutheast Jan 2015
Solar project 116, Polk County
Solar
19.7 MWWithdrawn / abandoned Polk, FLSoutheast Dec 2024target 2025
Solar project IC-418, Greene County
Solar
19.7 MWWithdrawn / abandoned Greene, ALSoutheast Aug 2015
Solar project IC-409, Long County
Solar
19.7 MWWithdrawn / abandoned Long, GASoutheast Feb 2015
Page 51 of 55

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)