πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· SOUTHEAST

Solar project IC-635

Solar project IC-635 is a 19.8 MW solar request withdrawn in the Southeast interconnection queue, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-635
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Thomson Primary - Culpepper Lumber 46kV Line
Technology
Solar: 19.8 MW
Total requested
19.8 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
27 April 2017
Withdrawn
July 2017

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem