United States βΊ Grid βΊ Interconnection queues βΊ Tennessee
SOLAR Β· SOUTHEASTSolar project 268, Hardeman County
Solar project 268, Hardeman County is a 20.0 MW solar request withdrawn in the Southeast interconnection queue, in Hardeman County, Tennessee, connecting to Tennessee Valley Authority.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 268
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Tennessee Valley Authority
- Location
- Hardeman County, Tennessee
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 27 April 2015
Location
Marker shows the centre of Hardeman County; the queue data does not give exact sites.
Power plants in Tennessee Β· Transmission lines in Tennessee
Other requests in Hardeman County
- Solar + storage project 25RSC-009, Hardeman CountySolar + storage Β· 250 MW Β· in study
- Other project 79, Hardeman CountyOther Β· 20.0 MW Β· built
- Other project 79Other Β· 20.0 MW Β· built
- Solar + storage project 477, Hardeman CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project 399, Hardeman CountySolar Β· 150 MW Β· withdrawn
- Solar project 384, Hardeman CountySolar Β· 83.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem