🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown88792.3 GW
Active in queue16.0 GW71 requests
Agreement signed1,225 MW24 requests
Withdrawn88792.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

887 requests · page 5 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AE2-039, Gloucester County
Solar
44.0 MWWithdrawn / abandoned Gloucester, NJPJM Jan 2019target 2022
Battery storage project AF2-023, Salem County
Battery storage
42.5 MWWithdrawn / abandoned Salem, NJPJM Nov 2019target 2021
Gas project Y2-110, Cape May County
Gas
40.0 MWWithdrawn / abandoned Cape May, NJPJM Nov 2012target 2016
Solar project AG2-627, Gloucester County
Solar · South Harrison Solar, LLC
40.0 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2024
Gas project C09, Bergen County
Gas
37.0 MWWithdrawn / abandoned Bergen, NJPJM Feb 2000
Solar project AE2-091, Cumberland County
Solar
35.0 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2019target 2022
Cape May Energy Center (CMEC)
Gas
34.0 MWWithdrawn / abandoned Cape May, NJPJM Apr 2012target 2021
Solar + storage project AG2-035, Salem County
Solar + storage · ACE Development Company, LLC
33.0 MWWithdrawn / abandoned Salem, NJPJM Nov 2020target 2021
Linden Cogen Uprate
Gas · East Coast Power LLC
32.0 MWWithdrawn / abandoned Union, NJNYISO Sep 2017
Santos Solar
Solar
31.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2020target 2023
Mt Hope Waterpower Project
Other
30.0 MWWithdrawn / abandoned Morris, NJPJM Jun 2006target 2013
Hydro project AG2-172, Warren County
Hydro
30.0 MWWithdrawn / abandoned Warren, NJPJM Feb 2021target 2022
Battery storage project AF2-026, Cumberland County
Battery storage
30.0 MWWithdrawn / abandoned Cumberland, NJPJM Nov 2019target 2021
Winslow Landfill Solar Farm
Solar · Winslow LF Solar Farm, LLC
29.4 MWWithdrawn / abandoned Camden, NJPJM Mar 2025target 2022
Gas project W3-125, Gloucester County
Gas
27.9 MWWithdrawn / abandoned Gloucester, NJPJM Oct 2010target 2011
Gas project T63, Cumberland County
Gas
27.2 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2007target 2009
Gas project H26, Gloucester County
Gas
25.0 MWWithdrawn / abandoned Gloucester, NJPJM Jan 2002target 2003
Other project AB1-031A
Other
25.0 MWWithdrawn / abandoned NJPJM Jul 2015
Gas project E04, Monmouth County
Gas
24.0 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2000
Mickleton Battery Storage
Battery storage
24.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2019target 2028
Other project T57, Cape May County
Other
22.2 MWWithdrawn / abandoned Cape May, NJPJM Sep 2007target 2009
Battery storage project AG2-531, Morris County
Battery storage · West Denville LLC
20.0 MWWithdrawn / abandoned Morris, NJPJM Mar 2021target 2022
Gateway Energy Center
Battery storage
20.0 MWWithdrawn / abandoned Middlesex, NJPJM Apr 2014target 2019
Solar project W1-103, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Battery storage project AD2-211, Monmouth County
Battery storage
20.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2018target 2018
Solar project W3-082, Cape May County
Solar
20.0 MWWithdrawn / abandoned Cape May, NJPJM Sep 2010target 2011
Solar project W1-068, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Apr 2010target 2011
Solar project W3-031, Burlington County
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Aug 2010target 2012
Solar project V4-029, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2011
Offshore wind project U2-044, Cape May County
Offshore wind
20.0 MWWithdrawn / abandoned Cape May, NJPJM Jun 2008target 2011
Solar + storage project AG1-510, Warren County
Solar + storage
20.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2020target 2024
Solar project V4-063, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jan 2010target 2011
Florence solar
Solar
20.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2010target 2014
Solar project W3-164, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2011
Battery storage project AF1-160, Camden County
Battery storage
20.0 MWWithdrawn / abandoned Camden, NJPJM Sep 2019target 2021
Upper Pittsgrove Township - Site 5
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2016
Onshore wind project X1-112, Salem County
Onshore wind
20.0 MWWithdrawn / abandoned Salem, NJPJM Apr 2011target 2012
Mansfield #2
Battery storage
20.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2019target 2021
Milford Solar
Solar
20.0 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2010target 2018
Battery storage project AG2-533, Warren County
Battery storage · AF1327 LLC
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2025target 2021
Upper Pittsgrove Township - Site 4
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2016
Solar project W2-025, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM May 2010target 2011
Solar project W1-021, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2010target 2011
Solar project AG2-588, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2021target 2024
Solar project W1-118, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Onshore wind project W3-039, Hudson County
Onshore wind
20.0 MWWithdrawn / abandoned Hudson, NJPJM Aug 2010target 2012
Solar project W4-028, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2010target 2011
Solar project W2-101, Salem County
Solar
20.0 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2017
Solar project W4-100, Hunterdon County
Solar
20.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2011target 2012
Solar project W1-117, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Page 5 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)