United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in SPP (Southwest Power Pool) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21237.6 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

212 requests · page 5 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-075, Holt County
Onshore wind
50.0 MWAgreement signed Holt, NESPP Mar 2016target 2027
Solar project GEN-2021-SR8, Harper County
Solar
42.0 MWAgreement signed Harper, KSSPP May 20212023
Solar project GEN-2016-147, Cheyenne County
Solar
40.0 MWAgreement signed Cheyenne, NESPP Nov 20162024
Battery storage project GEN-2024-SR14, Lea County
Battery storage
36.0 MWAgreement signed Lea, NMSPP Jul 2024target 2026
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026
Other project GEN-2024-GR4, Cherokee County
Other
27.1 MWAgreement signed Cherokee, KSSPP Jul 2024target 2026
Onshore wind project GEN-2019-001, Pratt County
Onshore wind
25.0 MWAgreement signed Pratt, KSSPP Nov 20182025
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024
Solar project GEN-2020-056, Russell County
Solar
20.0 MWAgreement signed Russell, KSSPP Apr 20202025
Battery storage project GEN-2016-160, Ellis County
Battery storage
20.0 MWAgreement signed Ellis, KSSPP Nov 2016target 2026
Gas project GEN-2019-019, Woodbury County
Gas
15.2 MWAgreement signed Woodbury, IASPP Apr 20192022
Battery storage project GEN-2017-198, Douglas County
Battery storage
11.6 MWAgreement signed Douglas, NESPP Nov 2017target 2027
Page 5 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)