United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Southeast (non-ISO utilities) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,738603.3 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,738 requests · page 4 of 55
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project IC-031, Richmond County
Gas
787 MWWithdrawn / abandoned Richmond, GASoutheast
Gas project IC-255, Jackson County
Gas
782 MWWithdrawn / abandoned Jackson, GASoutheast Jun 2011
Gas project IC-250, Upson County
Gas
782 MWWithdrawn / abandoned Upson, GASoutheast Feb 2011
Gas project IC-005, Calhoun County
Gas
776 MWWithdrawn / abandoned Calhoun, ALSoutheast
Gas project IC-221, Jackson County
Gas
761 MWWithdrawn / abandoned Jackson, GASoutheast Jul 2007
Gas project 25-IC-1328, Stewart County
Gas
759 MWWithdrawn / abandoned Stewart, GASoutheast Apr 2025
Gas project 569364, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Gas project 564266, Cherokee County
Gas
757 MWWithdrawn / abandoned Cherokee, SCSoutheast Jun 2022
Other project 179, Madison County
Other
752 MWWithdrawn / abandoned Madison, TNSoutheast Aug 2001
Gas project 225, Shelby County
Gas
751 MWWithdrawn / abandoned Shelby, TNSoutheast Oct 2010
Other project 110, Shelby County
Other
750 MWWithdrawn / abandoned Shelby, TNSoutheast Jul 2000
Other project 146, Muhlenberg County
Other
750 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Feb 2001
Other project 51, Union County
Other
750 MWWithdrawn / abandoned Union, MSSoutheast Jun 1999
Gas project LGE-GIS-2007-001, Muhlenberg County
Gas
750 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Feb 2007target 2015
Other project 145, Muhlenberg County
Other
750 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Feb 2001
Gas project 20197, Anderson County
Gas
747 MWWithdrawn / abandoned Anderson, SCSoutheast Feb 2018
Gas project 420, St Johns County
Gas · Third Party
744 MWWithdrawn / abandoned St Johns, FLSoutheast Mar 2021target 2027
Gas project IC-071, Mitchell County
Gas
741 MWWithdrawn / abandoned Mitchell, GASoutheast
Gas project 21177, Cherokee County
Gas
741 MWWithdrawn / abandoned Cherokee, SCSoutheast Mar 2018
Gas project IC-758, Bay County
Gas
741 MWWithdrawn / abandoned Bay, FLSoutheast Dec 2018
Gas project 20200910002, Berkeley County
Gas
720 MWWithdrawn / abandoned Berkeley, SCSoutheast target 2024
Gas project 13, Polk County
Gas · Duke Energy Florida, LLC
720 MWWithdrawn / abandoned Polk, FLSoutheast Jun 2001
Nuclear project 240, Anderson County
Nuclear
720 MWWithdrawn / abandoned Anderson, TNSoutheast Apr 2013
Gas project 977574, Spartanburg County
Gas
710 MWWithdrawn / abandoned Spartanburg, SCSoutheast Jun 2025
Gas project LGE-GIS-2010-002, Jefferson County
Gas
704 MWWithdrawn / abandoned Jefferson, KYSoutheast Nov 2010target 2016
Gas project 977563, Rowan County
Gas
703 MWWithdrawn / abandoned Rowan, NCSoutheast Jun 2025
Solar project 66858, Columbus County
Solar · Masked
700 MWWithdrawn / abandoned Columbus, NCSoutheast Feb 2020
Gas project 10, Citrus County
Gas · Duke Energy Florida, LLC
700 MWWithdrawn / abandoned Citrus, FLSoutheast Nov 2000
Gas project IC-891, Coweta County
Gas
700 MWWithdrawn / abandoned Coweta, GASoutheast Jul 2020
Other project 34, Shelby County
Other
700 MWWithdrawn / abandoned Shelby, TNSoutheast Feb 1999
Other project 2, Lowndes County
Other
700 MWWithdrawn / abandoned Lowndes, MSSoutheast May 1998
Other project 32, Shelby County
Other
700 MWWithdrawn / abandoned Shelby, TNSoutheast Feb 1999
Coal project IC-217, Early County
Coal
700 MWWithdrawn / abandoned Early, GASoutheast Nov 2006
Other project 26, Humphreys County
Other
700 MWWithdrawn / abandoned Humphreys, TNSoutheast Dec 1998
Other project 36, Shelby County
Other
700 MWWithdrawn / abandoned Shelby, TNSoutheast Feb 1999
Other project 43, Shelby County
Other
700 MWWithdrawn / abandoned Shelby, TNSoutheast Apr 1999
Other project 7, Wilson County
Other
700 MWWithdrawn / abandoned Wilson, TNSoutheast May 1998
Gas project IC-890, Coweta County
Gas
700 MWWithdrawn / abandoned Coweta, GASoutheast Jul 2020
Other project 9, Humphreys County
Other
700 MWWithdrawn / abandoned Humphreys, TNSoutheast May 1998
Coal project IC-222, Early County
Coal
700 MWWithdrawn / abandoned Early, GASoutheast Oct 2007
Other project 30, Shelby County
Other
700 MWWithdrawn / abandoned Shelby, TNSoutheast Feb 1999
Gas project 63826, Rowan County
Gas
692 MWWithdrawn / abandoned Rowan, NCSoutheast Jan 2020
Gas project LGE-GIS-2010-003, Muhlenberg County
Gas
690 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Nov 2010target 2018
Gas project LGE-GIS-2009-002, Muhlenberg County
Gas
690 MWWithdrawn / abandoned Muhlenberg, KYSoutheast target 2017
Gas project IC-1253, Baldwin County
Gas
684 MWWithdrawn / abandoned Baldwin, ALSoutheast Mar 2024
Other project 174, Monroe County
Other
683 MWWithdrawn / abandoned Monroe, KYSoutheast Aug 2001
Other project 178, Madison County
Other
683 MWWithdrawn / abandoned Madison, TNSoutheast Aug 2001
Gas project IC-112, Calhoun County
Gas
676 MWWithdrawn / abandoned Calhoun, ALSoutheast
Gas project IC-224, Lee County
Gas
667 MWWithdrawn / abandoned Lee, ALSoutheast Nov 2007
Gas project 9, Lake County
Gas · Duke Energy Florida, LLC
662 MWWithdrawn / abandoned Lake, FLSoutheast Jul 2000
Page 4 of 55

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)