Requests shown658,251 MW
Active in queue19.7 GW185 requests
Agreement signed8,251 MW65 requests
Withdrawn59480.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

65 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
White Trillium
Solar
49.9 MWAgreement signed Van Wert, OHPJM Mar 2019target 2027
Eaton OH Solar
Solar
49.9 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Timber Road Solar Park III
Solar
49.9 MWAgreement signed Paulding, OHPJM Sep 2020target 2029
Solar project AF2-298, Montgomery County
Solar
49.9 MWAgreement signed Montgomery, OHPJM Mar 2020target 2028
Woodsdale Renewable Energy Center
Solar
49.0 MWAgreement signed Butler, OHPJM Mar 2019target 2026
Great Bend
Solar
48.0 MWAgreement signed Meigs, OHPJM Oct 2016target 2025
Hillclimber Solar
Battery storage
40.0 MWAgreement signed Champaign, OHPJM Jul 2019target 2029
Hillclimber Solar
Solar
38.5 MWAgreement signed Champaign, OHPJM Jul 2019target 2029
West Lorain Power Plant 345 kV
Gas
33.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2031
Scioto Solar
Solar
30.0 MWAgreement signed Hardin, OHPJM Mar 2019target 2026
Eaton OH Solar
Solar
20.0 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Angelina Solar I
Solar
18.0 MWAgreement signed Preble, OHPJM Aug 2019target 2028
Juliet Energy
Solar · Juliet Energy Project, LLC
12.0 MWAgreement signed Wood, OHPJM Feb 2020target 2027
West Lorain 138 kV Power Plant
Gas
11.3 MWAgreement signed Lorain, OHPJM Sep 2020target 2028
West Lorain 138 kV Power Plant
Gas
8.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2028
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)