United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Minnesota (2025 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5412.7 GW
Active in queue12.7 GW54 requests
Agreement signed0.0 MW0 requests
Withdrawn82,212 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

54 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J4009, Marshall County
Solar
80.0 MWIn study Marshall, MNMISO Apr 2025target 2030
Surplus; J1325
Battery storage
72.0 MWIn study Rock, MNMISO Feb 2025target 2027
Mount Simon Station
Gas Β· Rochester Public Utilities
49.5 MWIn study Olmsted, MNMISO Aug 2025target 2028
Hydro project J4200, Ramsey County
Hydro
16.0 MWIn study Ramsey, MNMISO Sep 2025target 2008
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)