United States › Grid › Interconnection queues › New Jersey

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown88792.3 GW
Active in queue16.0 GW71 requests
Agreement signed1,225 MW24 requests
Withdrawn88792.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

887 requests · page 10 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project X1-052, Burlington County
Solar
10.0 MWWithdrawn / abandoned Burlington, NJPJM Mar 2011target 2012
Solar project V4-078, Salem County
Solar
10.0 MWWithdrawn / abandoned Salem, NJPJM Jan 2010target 2011
Solar project X2-097, Sussex County
Solar
10.0 MWWithdrawn / abandoned Sussex, NJPJM Jul 2011target 2013
BKB Properties
Solar
10.0 MWWithdrawn / abandoned Mercer, NJPJM Apr 2011target 2012
Bristol-Myers
Solar
10.0 MWWithdrawn / abandoned Mercer, NJPJM Apr 2011target 2013
Solar project W4-018, Gloucester County
Solar
10.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2010target 2012
Gas project Y3-047, Essex County
Gas
10.0 MWWithdrawn / abandoned Essex, NJPJM Feb 2013target 2013
Solar project AC2-193, Camden County
Solar
10.0 MWWithdrawn / abandoned Camden, NJPJM Mar 2017target 2017
Solar project X3-027, Ocean County
Solar
10.0 MWWithdrawn / abandoned Ocean, NJPJM Aug 2011target 2012
Solar project X2-098, Warren County
Solar
10.0 MWWithdrawn / abandoned Warren, NJPJM Jul 2011target 2013
Solar project X2-016, Gloucester County
Solar
10.0 MWWithdrawn / abandoned Gloucester, NJPJM May 2011target 2013
Battery storage project Z2-095, Sussex County
Battery storage
10.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2014target 2015
Andover Solar Farm
Solar
10.0 MWWithdrawn / abandoned Sussex, NJPJM Oct 2011target 2015
Cloverleaf Solar Farm
Solar
10.0 MWWithdrawn / abandoned Monmouth, NJPJM Jun 2011target 2014
Solar project AD1-027, Camden County
Solar
10.0 MWWithdrawn / abandoned Camden, NJPJM Jul 2017target 2017
Garboski I Solar Farm
Solar
10.0 MWWithdrawn / abandoned Hunterdon, NJPJM Oct 2010target 2014
English SP
Solar
10.0 MWWithdrawn / abandoned Middlesex, NJPJM Aug 2009target 2010
Solar project AB2-044, Middlesex County
Solar
10.0 MWWithdrawn / abandoned Middlesex, NJPJM Feb 2016target 2017
Solar project X3-016, Salem County
Solar
10.0 MWWithdrawn / abandoned Salem, NJPJM Aug 2011target 2011
Solar project W1-055, Warren County
Solar
10.0 MWWithdrawn / abandoned Warren, NJPJM Mar 2010target 2011
Other project Z2-004, Gloucester County
Other
10.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2013target 2014
Solar project W4-099, Cumberland County
Solar
10.0 MWWithdrawn / abandoned Cumberland, NJPJM Jan 2011target 2011
Solar project W1-094, Gloucester County
Solar
10.0 MWWithdrawn / abandoned Gloucester, NJPJM Apr 2010target 2011
Broadway Solar Farm
Solar
10.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2017
Quakertown Solar Farm #2
Solar
10.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jun 2011target 2016
Railroad Avenue Energy Storage
Battery storage
10.0 MWWithdrawn / abandoned Hudson, NJPJM Apr 2020target 2025
Solar project X1-051, Burlington County
Solar
10.0 MWWithdrawn / abandoned Burlington, NJPJM Mar 2011target 2012
Solar project AB1-104, Camden County
Solar
9.9 MWWithdrawn / abandoned Camden, NJPJM Oct 2015target 2016
Meadows at Mansfield Solar Farm
Solar
9.7 MWWithdrawn / abandoned Warren, NJPJM Feb 2011target 2014
Solar project W4-040, Gloucester County
Solar
9.7 MWWithdrawn / abandoned Gloucester, NJPJM Dec 2010target 2012
Solar project X1-004, Hunterdon County
Solar
9.7 MWWithdrawn / abandoned Hunterdon, NJPJM Feb 2011target 2011
Solar project X1-102, Warren County
Solar
9.5 MWWithdrawn / abandoned Warren, NJPJM Apr 2011target 2012
Gas project B13, Ocean County
Gas
9.0 MWWithdrawn / abandoned Ocean, NJPJM Jul 1999
Solar project AC2-134, Sussex County
Solar
9.0 MWWithdrawn / abandoned Sussex, NJPJM Mar 2017target 2018
Solar project W1-066, Camden County
Solar
9.0 MWWithdrawn / abandoned Camden, NJPJM Mar 2010target 2010
Gas project D13, Middlesex County
Gas
9.0 MWWithdrawn / abandoned Middlesex, NJPJM Jul 2000
Red Valley Solar Farm
Solar
9.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2011target 2016
CleanLight Mansfield Solar Project
Solar
9.0 MWWithdrawn / abandoned Burlington, NJPJM Jan 2011target 2012
Gas project X1-001, Cumberland County
Gas
9.0 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2011target 2011
Solar project W4-061, Mercer County
Solar
9.0 MWWithdrawn / abandoned Mercer, NJPJM Jan 2011target 2012
Burlington 26 kV Solar
Solar
8.8 MWWithdrawn / abandoned Burlington, NJPJM Jul 2016target 2021
Solar project W1-092, Cumberland County
Solar
8.7 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2010target 2011
Solar project AH1-067, Gloucester County
Solar
8.5 MWWithdrawn / abandoned Gloucester, NJPJM Jul 2021target 2023
Solar project W2-031, Gloucester County
Solar
8.5 MWWithdrawn / abandoned Gloucester, NJPJM Jun 2010target 2012
Mansfield Solar
Solar
8.3 MWWithdrawn / abandoned Burlington, NJPJM Oct 2010target 2012
Other project T61, Ocean County
Other
8.3 MWWithdrawn / abandoned Ocean, NJPJM Sep 2007target 2009
Solar project W3-056, Burlington County
Solar
8.0 MWWithdrawn / abandoned Burlington, NJPJM Sep 2010target 2013
Solar project W3-100, Salem County
Solar
8.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2010target 2012
Solar project X1-101, Hunterdon County
Solar
8.0 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2011target 2012
White Township Solar Farm
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Jan 2011target 2014
Page 10 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)