United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Southeast (non-ISO utilities) — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,738603.3 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,738 requests · page 10 of 55
ProjectCapacityStatusLocationRegionQueuedOnline
Other project IC-861, Baldwin County
Other
400 MWWithdrawn / abandoned Baldwin, ALSoutheast Apr 2020target 2024
Solar project 146, Marion County
Solar
400 MWWithdrawn / abandoned Marion, SCSoutheast May 2020target 2023
Solar + storage project 520, Panola County
Solar + storage
400 MWWithdrawn / abandoned Panola, MSSoutheast Sep 2022target 2024
Gas project IC-249, Upson County
Gas
391 MWWithdrawn / abandoned Upson, GASoutheast Feb 2011
Gas project IC-254, Jackson County
Gas
391 MWWithdrawn / abandoned Jackson, GASoutheast Jun 2011
Gas project IC-225, Jackson County
Gas
386 MWWithdrawn / abandoned Jackson, GASoutheast Dec 2007
Gas project IC-226, Jackson County
Gas
386 MWWithdrawn / abandoned Jackson, GASoutheast Dec 2007
Gas project 16, Polk County
Gas · Duke Energy Florida, LLC
380 MWWithdrawn / abandoned Polk, FLSoutheast May 2002
Gas project 15, Osceola County
Gas · Duke Energy Florida, LLC
368 MWWithdrawn / abandoned Osceola, FLSoutheast Apr 2002
Gas project 38, Polk County
Gas · Duke Energy Florida, LLC
368 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2002
Gas project 149, Georgetown County
Gas
360 MWWithdrawn / abandoned Georgetown, SCSoutheast May 2020target 2024
Gas project 20200728001, Jasper County
Gas
360 MWWithdrawn / abandoned Jasper, SCSoutheast target 2024
Gas project 150, Georgetown County
Gas
360 MWWithdrawn / abandoned Georgetown, SCSoutheast May 2020target 2024
Solar project GI-97, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Jan 2022target 2024
Solar project IC-712, Calhoun County
Solar
350 MWWithdrawn / abandoned Calhoun, FLSoutheast Jun 2018
Other project 25, Humphreys County
Other
350 MWWithdrawn / abandoned Humphreys, TNSoutheast Dec 1998
Other project 12, Colbert County
Other
350 MWWithdrawn / abandoned Colbert, ALSoutheast Jun 1998
Battery storage project 899003, Chatham County
Battery storage · Masked
350 MWWithdrawn / abandoned Chatham, NCSoutheast Jun 2023
Solar project 119, Dorchester County
Solar
350 MWWithdrawn / abandoned Dorchester, SCSoutheast Dec 2018target 2021
Solar project GI-106, New Madrid County
Solar
350 MWWithdrawn / abandoned New Madrid, MOSoutheast Aug 2022target 2024
Other project 41, Colbert County
Other
350 MWWithdrawn / abandoned Colbert, ALSoutheast Mar 1999
Other project 8, Warren County
Other
350 MWWithdrawn / abandoned Warren, KYSoutheast May 1998
Gas project 138414, Gaston County
Gas
348 MWWithdrawn / abandoned Gaston, NCSoutheast Oct 2020
Gas project 77, Pasco County
Gas · Masked
345 MWWithdrawn / abandoned Pasco, FLSoutheast Jan 2008target 2009
Solar project IC-794, Turner County
Solar
343 MWWithdrawn / abandoned Turner, GASoutheast May 2019
Other project 125, Mccracken County
Other
340 MWWithdrawn / abandoned Mccracken, KYSoutheast Nov 2000
Other project 151, Gibson County
Other
340 MWWithdrawn / abandoned Gibson, TNSoutheast Mar 2001
Solar project 353, Fayette County
Solar
340 MWWithdrawn / abandoned Fayette, TNSoutheast Jun 2018
Other project 189, Gibson County
Other
340 MWWithdrawn / abandoned Gibson, TNSoutheast Feb 2002
Other project 194, Panola County
Other
329 MWWithdrawn / abandoned Panola, MSSoutheast Apr 2002
Other project 167, Panola County
Other
329 MWWithdrawn / abandoned Panola, MSSoutheast Jun 2001
Other project 118, Kemper County
Other
320 MWWithdrawn / abandoned Kemper, MSSoutheast Sep 2000
Other project 87, Maury County
Other
320 MWWithdrawn / abandoned Maury, TNSoutheast Mar 2000
Gas project IC-024, Floyd County
Gas
320 MWWithdrawn / abandoned Floyd, GASoutheast
Other project 29, Wilson County
Other
320 MWWithdrawn / abandoned Wilson, TNSoutheast Dec 1998
Other project 89, Maury County
Other
320 MWWithdrawn / abandoned Maury, TNSoutheast Mar 2000
Gas project IC-127, Jones County
Gas
320 MWWithdrawn / abandoned Jones, MSSoutheast
Other project 120, Warren County
Other
320 MWWithdrawn / abandoned Warren, KYSoutheast Sep 2000
Solar project 25-IC-1348, Burke County
Solar
320 MWWithdrawn / abandoned Burke, GASoutheast Apr 2025
Other project 119, Warren County
Other
320 MWWithdrawn / abandoned Warren, KYSoutheast Sep 2000
Other project 63, Leake County
Other
316 MWWithdrawn / abandoned Leake, MSSoutheast Sep 1999
Other project 60, Warren County
Other
316 MWWithdrawn / abandoned Warren, KYSoutheast Sep 1999
Other project 69, Warren County
Other
316 MWWithdrawn / abandoned Warren, KYSoutheast Nov 1999
Solar project 20240829003, Orangeburg County
Solar
300 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2028
Battery storage project 624, Indian River County
Battery storage · FPL
300 MWWithdrawn / abandoned Indian River, FLSoutheast Jan 2024target 2031
Solar project GI-74, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Solar + storage project 25-IC-AD, Decatur County
Solar + storage
300 MWWithdrawn / abandoned Decatur, GASoutheast
Battery storage project LGE-GIS-2021-011, Jefferson County
Battery storage
300 MWWithdrawn / abandoned Jefferson, KYSoutheast Mar 2021target 2026
Solar project GI-72, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Nov 2018target 2021
Solar + storage project IC-845, Mobile County
Solar + storage
300 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2020
Page 10 of 55

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)