Rampion is a 400 MW offshore wind farm in South East England, operated by RWE Npower. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Offshore
  • South East
  • England

Key facts

Installed capacity
400 MW
Status
Operational
Technology
Wind Β· Offshore
Operator
RWE Npower
Region
South East
Country
England
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
50.7412, -0.2298

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Rampion compares

16th of 488largest wind farms in the UK register
2nd of 7in South East
1.4%of listed UK wind farms capacity
β‰ˆ 1,332 GWhillustrative output a year

At a typical UK load factor for this technology (about 38% of the maximum possible output), a 400 MW station would generate roughly 1,332 GWh of electricity in a year, similar to the annual use of about 493,400 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in South East All run by RWE Npower

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Rampion Offshore Wind Farm (Hastings Zone)
Developer / operator
E.ON UK
Planning authority
The Planning Inspectorate - National Infrastructure
Planning reference
EN010032
Application submitted
25 March 2013
Permission granted
16 July 2014
Construction started
25 January 2016
Began operating
26 November 2017
Capacity in planning record
400 MW
Address
off the Sussex coastline, Offshore
REPD reference
2520

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.