WIND Β· OPERATIONAL

Millennium

Millennium is a 65 MW onshore wind farm in Scotland, operated by Falck Renewables SpA. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland
Project stageOperating
  1. PlanningDec 2003 (completed)
  2. ConsentedApr 2005 (completed)
  3. ConstructionJun 2006 (completed)
  4. OperatingJul 2008 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
65 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Falck Renewables SpA
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
57.1552, -4.8836

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Millennium compares

83rd of 488largest wind farms in the UK register
43rd of 199in Scotland
0.22%of listed UK wind farms capacity
β‰ˆ 148 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 65 MW station would generate roughly 148 GWh of electricity in a year, similar to the annual use of about 54,830 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Falck Renewables SpA

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Millennium Windfarm
Developer / operator
Renewable Development Company (RDC) Scotland (Ltd) for FALCK RENEWABLES
Planning authority
Highland
Planning reference
03/00505/FULL
Application submitted
1 December 2003
Permission granted
1 April 2005
Construction started
1 June 2006
Began operating
15 July 2008
Capacity in planning record
40 MW
Address
Millennium Windfarm on The Achlain and Invergarry amd Aberchalder Estates Glengarry Invergarry Inverness-Shire (nr Glen Moriston Fort Augustus), Highland
REPD reference
4682

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.