SOLAR Β· OPERATIONAL

Malmaynes

Malmaynes is a 14.8 MW solar farm in South East England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South East
  • England

Key facts

Installed capacity
14.8 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
South East
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
ME3 9SQ
Coordinates
51.4482, 0.5985

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Malmaynes compares

81st of 662largest solar farms in the UK register
13th of 105in South East
0.26%of listed UK solar farms capacity
β‰ˆ 13 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 14.8 MW station would generate roughly 13 GWh of electricity in a year, similar to the annual use of about 4,810 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South East All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
MALMAYNES HALL FARM
Developer / operator
Wessex Solar Energy
Planning authority
Medway
Planning reference
MC/14/2082
Application submitted
31 July 2014
Permission granted
6 November 2014
Construction started
15 November 2014
Began operating
31 March 2015
Capacity in planning record
12 MW
Address
LAND OFF MALMAYNES HALL FARM, MALMAYNES HALL ROAD, STOKE, ROCHESTER, KENT, Kent
REPD reference
2135

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.