River Cuileig is a 3.3 MW small hydro scheme in Scotland, operated by SSE Group. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Small Hydro
- Scotland
Key facts
- Installed capacity
- 3.3 MW
- Status
- Operational
- Technology
- Hydro Β· Small Hydro
- Operator
- SSE Group
- Region
- Scotland
- Country
- Scotland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 57.7633, -5.0392
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How River Cuileig compares
At a typical UK load factor for this technology (about 35% of the maximum possible output), a 3.3 MW station would generate roughly 10 GWh of electricity in a year, similar to the annual use of about 3,750 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Hydroelectric stations generate electricity from water flowing downhill through turbines, either from a reservoir behind a dam or from a river (run-of-river). Most UK hydro capacity is in Scotland and Wales.
All UK hydro schemes and pumped-storage stations Hydro schemes and pumped-storage stations in Scotland All run by SSE GroupNearby generating sites
- Inverlael Β· 2.5 MW small hydro scheme6.6 km
- Vaich Power Station Β· 0.32 MW small hydro scheme15.5 km
- Lochluichart Β· 69 MW onshore wind farm17.9 km
- Achanalt Power Station - A Β· 3.1 MW small hydro scheme18.5 km
- Corriemoillie Β· 48.5 MW onshore wind farm19.0 km
- Grudie Bridge Power Station - A, G Β· 18.7 MW hydroelectric station20.4 km
- Luichart Β· 34 MW hydroelectric station20.8 km
- Mossford Power Station - A,G Β· 18.7 MW hydroelectric station20.8 km
Also operated by SSE Group
SSE Group operates 127 sites in the register. Largest first:
- Peterhead Β· gas-fired power station1,180 MW
- Seagreen Β· offshore wind farm1,075 MW
- Keadby 2 Β· gas-fired power station840 MW
- Medway Β· gas-fired power station755 MW
- Keadby Β· CCGT gas power station735 MW
- Beatrice Offshore windfarm Β· offshore wind farm588 MW
- Greater Gabbard Β· offshore wind farm504 MW
- Viking Wind Farm Β· onshore wind farm443 MW
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Cuileig Hydro Scheme
- Developer / operator
- Scottish Hydro-Electric plc
- Planning authority
- Highland
- Application submitted
- 9 October 1998
- Permission granted
- 1 March 2000
- Began operating
- 15 February 2002
- Capacity in planning record
- 3.3 MW
- Address
- Abhainn Cuileig Braemore Junction Ross and Cromarty, Highland
- REPD reference
- 434
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.