Grid upgrades Β· Peterhead / Boddam, Aberdeenshire

Peterhead / Boddam 275 kV Substation Transformer Upgrade

Under construction

SSEN reports first-phase construction underway in July 2026, including platform earthworks, drainage and a SuDS pond. Balfour Beatty is carrying out the works. Construction is expected to finish by 2028, with commissioning and energisation by 2030. This is separate from the EGL2 HVDC converter and existing power station.

Sources reviewed 2026-10-08 Β· SSEN Transmission

Project facts

StatusUnder construction
Developer / operatorSSEN Transmission
RegionPeterhead / Boddam, Aberdeenshire
CountryScotland
Published ratingNot published
Rating definitionAC transformer replacement and network reinforcement; no extra generating capacity
Connection / routeExisting Peterhead 275 kV substation near Boddam
Delivery target2030 (developer target; subject to change)
Voltage275 kV

What this link contributes

This asset provides a route for electricity to move between networks or strengthens the network carrying that electricity. Its capacity cannot be added to wind, solar or power-station capacity as though it were another generator.

Existing Peterhead 275 kV substation near Boddam

Converter stations, cable manufacture, offshore installation, landfall works and grid energisation can progress at different times. The status above describes the documented project stage rather than assuming all work packages are complete.

Project location

SSEN places the upgrade at the existing Peterhead substation near Boddam. An exact work-package position has not been verified; this map provides geographic context only.

Loading OpenStreetMap…

The map shows geographical context only. No unverified site pin is displayed.

    Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2’s additional outlines and route layers are explicitly identified in the developer’s map data.

    Sources and review date

    1. Developer project information
      Reviewed 2026-10-08

    How Octary distinguishes proposals, published ratings and live measurements

    Report a correction with a source

    GRID CONTEXT

    Great Britain electricity now

    Explore the grid β†’
    Loading the latest published grid interval…

    National figures from the Carbon Intensity API. These do not measure an individual project’s output, cable flow or data-centre electricity use.