Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· SPTKilleal
Killeal is a 73 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Newton Stewart GSP, with capacity due from October 2036. The connection agreement is held by Abei Energy Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2036 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-006112
- Customer
- Abei Energy Limited
- Technology
- Wind Onshore
- Total capacity
- 73 MW
- Change in this agreement
- +73 MW
- Capacity effective from
- 31 October 2036
- Connection site
- Newton Stewart GSP
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem