🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · SHET

Rattray BESS and Solar Plant

Rattray BESS and Solar Plant is a 300 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at New North East Substation 400kV Substation, with capacity due from October 2037. The connection agreement is held by Greentech Projects Holding UK Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-006056
Customer
Greentech Projects Holding UK Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
300 MW
Change in this agreement
+300 MW
Capacity effective from
31 October 2037
Connection site
New North East Substation 400kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near New North East Substation · Grid map

Other projects at New North East Substation 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem