Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTGladsmuir Wind Farm
Gladsmuir Wind Farm is a 43 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at Harburn 132/33kV Grid Supply Point Substation, with capacity due from October 2032. The connection agreement is held by Wind Estate (UK) Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2032 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-005915
- Customer
- Wind Estate (UK) Limited
- Technology
- Wind Onshore
- Total capacity
- 43 MW
- Change in this agreement
- +43 MW
- Capacity effective from
- 29 October 2032
- Connection site
- Harburn 132/33kV Grid Supply Point Substation
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
Connection site
The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem