Grid infrastructure β€Ί Connection queue β€Ί Onshore wind

ONSHORE WIND Β· SHET

Hesta Head

Hesta Head is a 20 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Finstown (Orkney) GSP, with capacity due from April 2029. The connection agreement is held by Hesta Head Wind Farm Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-005100
Customer
Hesta Head Wind Farm Limited
Technology
Wind Onshore
Total capacity
20 MW
Change in this agreement
+20 MW
Capacity effective from
6 April 2029
Connection site
Finstown (Orkney) GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the place the connection site is named after, not the project itself, with the transmission network around it.

Projects connecting near Finstown (Orkney) GSP Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem