ONSHORE WIND · SHETPeninsula Energy Park
Peninsula Energy Park is a 250 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at PENINSULA ENERGY PARK 220kV SUBSTATION, with capacity due from October 2035. The connection agreement is held by Renantis UK Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2035 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004961
- Customer
- Renantis UK Limited
- Technology
- Wind Onshore
- Total capacity
- 250 MW
- Change in this agreement
- +250 MW
- Capacity effective from
- 31 October 2035
- Connection site
- PENINSULA ENERGY PARK 220kV SUBSTATION
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem