🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Hydro and pumped storage

HYDRO AND PUMPED STORAGE · SHET

Glen Earrach PSH

Glen Earrach PSH is a 1.8 GW hydro and pumped storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Glen Earrach PSH 400kV substation, with capacity due from October 2035. The connection agreement is held by Glen Earrach Energy Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2035 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004903
Customer
Glen Earrach Energy Limited
Technology
Pump Storage
Total capacity
1.8 GW
Change in this agreement
+1.8 GW
Capacity effective from
31 October 2035
Connection site
Glen Earrach PSH 400kV substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near Glen Earrach PSH · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem