Grid infrastructure › Connection queue › Onshore wind
ONSHORE WIND · SPTGrayside Wind Farm
Grayside Wind Farm is a 108 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at REDSHAW 132kV B BOARD SUBSTATION, with capacity due from October 2037. The connection agreement is held by Grayside Wf Ltd.
Project stageIn planning
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2037 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004563
- Customer
- Grayside Wf Ltd
- Technology
- Wind Onshore
- Total capacity
- 108 MW
- Change in this agreement
- +108 MW
- Capacity effective from
- 31 October 2037
- Connection site
- REDSHAW 132kV B BOARD SUBSTATION
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem