Grid infrastructure › Connection queue › Onshore wind

ONSHORE WIND · SPT

Grayside Wind Farm

Grayside Wind Farm is a 108 MW onshore wind project in planning, connecting to the SP Transmission (south Scotland) network at REDSHAW 132kV B BOARD SUBSTATION, with capacity due from October 2037. The connection agreement is held by Grayside Wf Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004563
Customer
Grayside Wf Ltd
Technology
Wind Onshore
Total capacity
108 MW
Change in this agreement
+108 MW
Capacity effective from
31 October 2037
Connection site
REDSHAW 132kV B BOARD SUBSTATION
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near REDSHAW · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem