Grid infrastructure β€Ί Connection queue β€Ί Gas

GAS Β· SHET

Peterhead Carbon Capture

Peterhead Carbon Capture is a 910 MW gas project in planning, connecting to the SSEN Transmission (north Scotland) network at Peterhead 275kV, with capacity due from October 2033. The connection agreement is held by Sse Thermal Generation (Scotland) Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004529
Customer
Sse Thermal Generation (Scotland) Limited
Technology
CCGT (Combined Cycle Gas Turbine)
Total capacity
910 MW
Change in this agreement
+910 MW
Capacity effective from
31 October 2033
Connection site
Peterhead 275kV
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Peterhead Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem