Glenmore

Glenmore is a 40 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Edinbane 132/33kV Substation, with capacity due from October 2034. The connection agreement is held by Aeuk Wind Project II Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2034 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004445
Customer
Aeuk Wind Project II Ltd
Technology
Wind Onshore
Total capacity
40 MW
Change in this agreement
+40 MW
Capacity effective from
31 October 2034
Connection site
Edinbane 132/33kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Edinbane Β· Grid map

Other projects at Edinbane 132/33kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem